Slack Lane, Westhoughton (45 MW battery storage)

Slack Lane, Westhoughton is a 45 MW battery storage project in Bolton, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 December 2024, not yet built; the record was last updated on 13 January 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

45 MWbattery storage
approved, not builtstatus in REPD
13 January 2025record last updated
Boltoncouncil area

Planning timeline

DateStage
28 August 2024Application submitted
24 December 2024Planning permission granted
24 December 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
45 MW
Status (REPD)
approved, not built
Record last updated
13 January 2025
Operator or applicant
Foundation Property & Capital Group
Planning authority
Bolton
Planning application reference
18884/24
Address (REPD)
West of Slack Lane, Westhoughton
Council area (by location)
Bolton
Time to decision
17 weeks
Name in REPD
Slack Lane, Westhoughton - Battery Energy Storage System
REPD reference
17105

Who decides

ApplicationsBoltonUK
Decided applications (solar, wind, battery)2210,236
Refused4 (18%)19%
Solar refused1 of 1512%
Onshore wind refused1 of 145%
Battery storage refused2 of 616%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Athertonbattery storage30operational3.6
Cleworth Hall Farmsolar farm5abandoned6.0
Orrell Street Battery Energy Storage Facilitybattery storage50approved, not built7.2
Whitehead Landfill Site, Lower Green Lane Solar Farmsolar farm10application submitted9.1
Bent Spur Solar Farmsolar farm5operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5582, -2.5192).