Atherton (30 MW battery storage)

Atherton is a 30 MW battery storage project in Wigan, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 10 September 2025; the record was last updated on 22 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWbattery storage
operationalstatus in REPD
22 September 2025record last updated
Wigancouncil area

Planning timeline

DateStage
15 February 2022Application submitted
29 July 2022Planning permission granted
1 September 2023Construction started
10 September 2025Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
30 MW
Status (REPD)
operational
Record last updated
22 September 2025
Operator or applicant
FPC Electric Land Limited / Pulse Clean Energy
Planning authority
Wigan
Planning application reference
A/22/93181/FULL
Address (REPD)
R/O 9 Coal Pit Lane Atherton Manchester
Council area (by location)
Wigan
Time to decision
23 weeks
Name in REPD
Atherton - Battery energy storage
REPD reference
11151

Who decides

ApplicationsWiganUK
Decided applications (solar, wind, battery)1710,236
Refused0 (0%)19%
Solar refused0 of 1312%
Battery storage refused0 of 416%
Median time from submission to decision9.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Slack Lane, Westhoughtonbattery storage45approved, not built3.6
Cleworth Hall Farmsolar farm5abandoned3.7
Whitehead Landfill Site, Lower Green Lane Solar Farmsolar farm10application submitted5.7
Duckinfield Farm, Hurst Lane Solar Farmsolar farm10approved, not built6.5
Lights Oaks Mosssolar farm5abandoned7.0
Orrell Street Battery Energy Storage Facilitybattery storage50approved, not built8.1
Kenyon Lanesolar farm5refused8.2
Bent Spur Solar Farmsolar farm5operational8.5
Silver Lane, Risley Solar Farmsolar farm5approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5268, -2.5039).