Energy Projects Near You

Duckinfield Farm, Hurst Lane Solar Farm (10 MW)

Duckinfield Farm, Hurst Lane Solar Farm is a 10 MW solar farm project in Warrington, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 May 2026, not yet built; the record was last updated on 8 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
approved, not builtstatus in REPD
8 June 2026record last updated
Warringtoncouncil area

Planning timeline

DateStage
14 July 2025Application submitted
22 May 2026Planning permission granted
22 May 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
approved, not built
Record last updated
8 June 2026
Operator or applicant
Noventum Power Limited
Planning authority
Warrington
Planning application reference
2025/00969/FULM
Site area
16.6 ha
Address (REPD)
Duckinfield Farm Hurst Lane, Culcheth And Glazebury
Council area (by location)
Warrington
Time to decision
45 weeks
Name in REPD
Duckinfield Farm, Hurst Lane - Solar Farm
REPD reference
16992

Who decides

ApplicationsWarringtonUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused5 of 3012%
Onshore wind refused0 of 145%
Battery storage refused1 of 416%
Median time from submission to decision7.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lights Oaks Mosssolar farm5abandoned1.5
Silver Lane, Risley Solar Farmsolar farm5approved, not built3.4
Kenyon Lanesolar farm5refused3.8
Whitehead Landfill Site, Lower Green Lane Solar Farmsolar farm10application submitted3.9
Athertonbattery storage30operational6.5
Cleworth Hall Farmsolar farm5abandoned7.1
Carrington Power Station, Manchester Roadbattery storage680under construction7.5
Wild Fowl Farm, Carrington Lanebattery storage35approved, not built9.5
Daines Battery Energy Storage Systembattery storage600approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4685, -2.5006).