Energy Projects Near You

Carrington Power Station, Manchester Road (680 MW battery storage)

Carrington Power Station, Manchester Road is a 680 MW battery storage project in Trafford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 November 2026; the record was last updated on 9 July 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

680 MWbattery storage
under constructionstatus in REPD
9 July 2026record last updated
Traffordcouncil area

Planning timeline

DateStage
23 February 2023Application submitted
20 July 2023Planning permission granted
1 November 2026Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
680 MW
Status (REPD)
under construction
Record last updated
9 July 2026
Operator or applicant
Statera Energy
Planning authority
Trafford
Planning application reference
110320/FUL/23
Address (REPD)
Carrington Power Station, Manchester Road
Council area (by location)
Trafford
Time to decision
21 weeks
Name in REPD
Carrington Power Station, Manchester Road - Battery Storage
REPD reference
13362

Who decides

ApplicationsTraffordUK
Decided applications (solar, wind, battery)2810,236
Refused6 (21%)19%
Solar refused3 of 1912%
Battery storage refused3 of 916%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wild Fowl Farm, Carrington Lanebattery storage35approved, not built2.2
Daines Battery Energy Storage Systembattery storage600approved, not built2.3
Lights Oaks Mosssolar farm5abandoned6.1
Silver Lane, Risley Solar Farmsolar farm5approved, not built6.6
Whitehead Landfill Site, Lower Green Lane Solar Farmsolar farm10application submitted6.7
Duckinfield Farm, Hurst Lane Solar Farmsolar farm10approved, not built7.5
Golf Roadbattery storage90approved, not built7.6
Sale Golf Club, Golf Roadbattery storage70approved, not built7.6
Freshfields, Fairy Lanebattery storage99.9under construction8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4334, -2.4035).