Golf Road (90 MW battery storage)
Golf Road is a 90 MW battery storage project in Trafford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 18 October 2024, not yet built; the record was last updated on 28 October 2024.
90 MWbattery storage
approved, not builtstatus in REPD
28 October 2024record last updated
Traffordcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 2 June 2023 | Application submitted |
| 10 January 2024 | Refused by the planning authority |
| 6 June 2024 | Appeal lodged |
| 18 October 2024 | Planning permission granted |
| 18 October 2024 | Appeal allowed |
Project details
- Technology
- battery storage (stand-alone storage)
- Capacity
- 90 MW
- Status (REPD)
- approved, not built
- Record last updated
- 28 October 2024
- Operator or applicant
- Cragside Energy Limited
- Planning authority
- Trafford
- Planning application reference
- 111105/FUL/23
- Appeal reference
- APP/Q4245/W/24/3343250
- Address (REPD)
- Golf Road, Sale
- Council area (by location)
- Trafford
- Time to decision
- 72 weeks
- Name in REPD
- Golf Road - Battery Energy Storage
- REPD reference
- 13459
Who decides
| Applications | Trafford | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 28 | 10,236 |
| Refused | 6 (21%) | 19% |
| Solar refused | 3 of 19 | 12% |
| Battery storage refused | 3 of 9 | 16% |
| Median time from submission to decision | 8.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Sale Golf Club, Golf Road | battery storage | 70 | approved, not built | <0.1 |
| Freshfields, Fairy Lane | battery storage | 99.9 | under construction | 0.7 |
| West Didsbury Battery Storage | battery storage | 50 | operational | 0.8 |
| Wild Fowl Farm, Carrington Lane | battery storage | 35 | approved, not built | 5.4 |
| Daines Battery Energy Storage System | battery storage | 600 | approved, not built | 5.7 |
| Carrington Power Station, Manchester Road | battery storage | 680 | under construction | 7.6 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4237, -2.2904).