Freshfields, Fairy Lane (99.9 MW battery storage)

Freshfields, Fairy Lane is a 99.9 MW battery storage project in Trafford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 January 2026; the record was last updated on 26 January 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

99.9 MWbattery storage
under constructionstatus in REPD
26 January 2026record last updated
Traffordcouncil area

Planning timeline

DateStage
25 October 2022Application submitted
20 March 2023Planning permission granted
1 January 2026Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
99.9 MW
Status (REPD)
under construction
Record last updated
26 January 2026
Operator or applicant
STOR Power Utilities Limited
Planning authority
Trafford
Planning application reference
109463/FUL/22
Address (REPD)
Freshfields Fairy Lane
Council area (by location)
Trafford
Time to decision
21 weeks
Name in REPD
Freshfields, Fairy Lane - Battery Storage
REPD reference
12694

Who decides

ApplicationsTraffordUK
Decided applications (solar, wind, battery)2810,236
Refused6 (21%)19%
Solar refused3 of 1912%
Battery storage refused3 of 916%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
West Didsbury Battery Storagebattery storage50operational0.1
Sale Golf Club, Golf Roadbattery storage70approved, not built0.7
Golf Roadbattery storage90approved, not built0.7
Wild Fowl Farm, Carrington Lanebattery storage35approved, not built6.0
Daines Battery Energy Storage Systembattery storage600approved, not built6.2
Carrington Power Station, Manchester Roadbattery storage680under construction8.2
Welkin Mill, Welkin Roadbattery storage49.9under construction9.7
Welkin Road, Bredburybattery storage20operational9.7
Bredbury Substationbattery storage49.9under construction9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4196, -2.2822).