West Didsbury Battery Storage (50 MW)

West Didsbury Battery Storage is a 50 MW battery storage project in Trafford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 21 November 2023; the record was last updated on 24 November 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
operationalstatus in REPD
24 November 2023record last updated
Traffordcouncil area

Planning timeline

DateStage
25 September 2017Application submitted
22 November 2019Planning permission granted
1 June 2022Construction started
21 November 2023Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
operational
Record last updated
24 November 2023
Operator or applicant
Statera Energy / Gresham House
Planning authority
Trafford
Planning application reference
92459/FUL/17
Address (REPD)
Sawfield Nurseries Fairy Lane, Sale
Council area (by location)
Trafford
Time to decision
113 weeks
REPD reference
7185

Who decides

ApplicationsTraffordUK
Decided applications (solar, wind, battery)2810,236
Refused6 (21%)19%
Solar refused3 of 1912%
Battery storage refused3 of 916%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Freshfields, Fairy Lanebattery storage99.9under construction0.1
Sale Golf Club, Golf Roadbattery storage70approved, not built0.8
Golf Roadbattery storage90approved, not built0.8
Wild Fowl Farm, Carrington Lanebattery storage35approved, not built6.1
Daines Battery Energy Storage Systembattery storage600approved, not built6.3
Carrington Power Station, Manchester Roadbattery storage680under construction8.3
Welkin Mill, Welkin Roadbattery storage49.9under construction9.6
Welkin Road, Bredburybattery storage20operational9.6
Bredbury Substationbattery storage49.9under construction9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4188, -2.2809).