Energy Projects Near You

Solar, wind and battery projects near Sale (M33)

73 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of M33 (Trafford): 5 are waiting for a planning decision, 56 approved but not yet running, 2 operational. The largest live scheme is Carrington Power Station, Manchester Road (680 MW battery storage, under construction since 1 November 2026), 5.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

73projects within 10 km
5awaiting a decision
56approved, not running
2operational

Projects within 10 km of M33

Projects of 1 MW and more (11)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Golf Roadbattery storagebattery storage90approved, not builtupdated Oct 2024Jun 2023granted Oct 2024Oct 2024Trafford2.4
Sale Golf Club, Golf Roadbattery storagebattery storage70approved, not builtupdated Nov 2023Apr 2023granted Nov 2023Nov 2023Trafford2.4
Freshfields, Fairy Lanebattery storagebattery storage99.9under constructionupdated Jan 2026Oct 2022granted Mar 2023Jan 2026Trafford2.9
West Didsbury Battery Storagebattery storagebattery storage50operationalupdated Nov 2023Sep 2017granted Nov 2019Nov 2023Trafford3.0
Wild Fowl Farm, Carrington Lanebattery storagebattery storage35approved, not builtupdated Mar 2025May 2024refused Aug 2024Mar 2025Trafford3.2
Daines Battery Energy Storage Systembattery storagebattery storage600approved, not builtupdated Jun 2025Oct 2024granted May 2025Jun 2025Trafford3.3
Carrington Power Station, Manchester Roadbattery storagebattery storage680under constructionupdated Jul 2026Feb 2023granted Jul 2023Jul 2026Trafford5.3
Tesco Store East Didsburyrooftop solarrooftop solar1approved, not builtupdated Feb 2021Nov 2019granted Jan 2020Feb 2021Manchester7.1
Sunbank Lane Solar Panelsrooftop solarrooftop solar1.5approved, not built may be out of dateupdated Jun 2021May 2021granted Jul 2021Jun 2021Manchester7.2
Sunbank Lanerooftop solarrooftop solar4.3approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Manchester7.6
Tesco Burnage Storerooftop solarrooftop solar1approved, not builtupdated Jun 2020Nov 2019granted Jan 2020Jun 2020Manchester7.7
Smaller schemes under 1 MW, mostly rooftop solar (60)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Springfield Primary School, Springfield Road Solar Panels Arrayrooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Jul 2025granted Sep 2025Dec 2025Trafford0.5
Dixons Brooklands Academy, Moor Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Manchester2.9
Timpson Roadrooftop solarrooftop solar0.5approved, not builtupdated Apr 2022Apr 2022granted May 2022Apr 2022Manchester3.3
Endress & Hauser, Floats Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Manchester3.4
Golden Way, Urmston - Unit 24 - Solar Panelsrooftop solarrooftop solar0.4approved, not builtupdated Oct 2024Jul 2024granted Sep 2024Oct 2024Trafford3.6
Lostock High Schoolrooftop solarrooftop solar0.2refusedupdated Dec 2025Aug 2025refused Oct 2025Dec 2025Trafford3.7
Longford Park School, Cromwell Roadrooftop solarrooftop solar0.4approved, not builtupdated Dec 2022Nov 2022granted Dec 2022Dec 2022Trafford3.7
Tesco Extra Altrinchamrooftop solarrooftop solar0.5under constructionupdated Sep 2020Jul 2020granted Sep 2020Sep 2020Trafford4.2
Flixton Road, Flixton - Micro Energy Storagebattery storagebattery storage0.2application submittedMay 2026——Trafford4.3
Acute Building, Southmoor Roadrooftop solarrooftop solar0.5approved, not builtupdated Mar 2026Nov 2025granted Jan 2026Mar 2026Manchester4.3
Wythenshawe Hospitalrooftop solarrooftop solar0.6application withdrawnupdated Feb 2022Jan 2022—Feb 2022Manchester4.3
Wythenshawe Hospitalrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Mar 2022Mar 2022granted May 2022Mar 2022Manchester4.3
Sainsburysrooftop solarrooftop solar0.4approved, not builtupdated Apr 2024Feb 2024granted Apr 2024Apr 2024Trafford4.4
Metrolink Trafford Depot, Warwick Road Solar Arraysrooftop solarrooftop solar0.3approved, not builtupdated Feb 2022Jan 2022granted Mar 2022Feb 2022Trafford4.7
Metrolink Trafford Depot Solar Panels & Battery Storagerooftop solarrooftop solar0.3refusedupdated Dec 2021May 2021refused Jul 2021Dec 2021Trafford4.7
Metrolink Trafford Depot Solar Panels & Battery Storagebattery storagebattery storage—refusedupdated Dec 2021May 2021refused Jul 2021Dec 2021Trafford4.7
Trafford General Hospital, Moorside Road Solar Arraysrooftop solarrooftop solar0.4approved, not builtupdated Jun 2026Feb 2026granted May 2026Jun 2026Trafford4.7
Central Park Estate, Trafford Park, Unit 22,rooftop solarrooftop solar0.5approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026Trafford4.9
Barton Dock Road, Trafford Parkrooftop solarrooftop solar0.3refusedupdated Dec 2025Sep 2025refused Oct 2025Dec 2025Trafford4.9
Fifth Avenue, Trafford Parkrooftop solarrooftop solar0.3approved, not builtupdated Jun 2022May 2022granted Jul 2022Jun 2022Trafford5.0
Gamma Telecom, Second Avenuerooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Jul 2025granted Sep 2025Dec 2025Trafford5.1
Bowless Exhibition, Longeridge Road Solar Panels Arrayrooftop solarrooftop solar1approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Trafford5.2
Pisces, Mosley Road, Unit Brooftop solarrooftop solar0.2approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Trafford5.3
CHEP Manchester, Trafford Parkrooftop solarrooftop solar0.3approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024Trafford5.3
DB Schenker, Mosley Road Solar Arraysrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Trafford5.5
Woodsend Road, Urmstonbattery storagebattery storage0.2application submittedMay 2026——Trafford5.7
Manchester Road - Green Hydrogen Production Facility & Battery Storagebattery storagebattery storage—approved, not built may be out of dateupdated Sep 2021Jul 2021granted Sep 2022Sep 2021Trafford5.7
Whalley Range High School, Wilbraham Roadrooftop solarrooftop solar0.4approved, not builtupdated Oct 2025Aug 2025granted Sep 2025Oct 2025Manchester5.8
David Lloyd Manchester, Barton Embankmentrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Trafford5.9
The Windrush Millenium Centre, Alexandra Roadrooftop solarrooftop solar—approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Manchester6.2
Loreto College, Chichester Roadrooftop solarrooftop solar0.4approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Manchester6.7
Scotscroft Towers Business Park, Wilmslow Roadrooftop solarrooftop solar0.1approved, not built may be out of dateupdated Feb 2024Jan 2024granted Feb 2024Feb 2024Manchester6.8
Barton Business Park, Cawdor Streetrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Salford6.8
Turnpike Depotsolar farmsolar farm0.5under constructionupdated May 2023May 2023—May 2023Salford6.8
Ferrous Wayrooftop solarrooftop solar0.3approved, not builtupdated Feb 2023Nov 2022granted Jan 2023Feb 2023Salford6.9
Ferrous Wayrooftop solarrooftop solar0.4approved, not builtupdated Feb 2025Jan 2025granted Mar 2025Feb 2025Salford6.9
Broadoak Comprehensive School, Warburton Lanerooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Aug 2025granted Oct 2025Dec 2025Trafford7.1
Manchester Metropolitan University, Birley Fieldsrooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Manchester7.2
Dnata City North, Pinfold Lanerooftop solarrooftop solar0.3approved, not builtupdated Aug 2025Jun 2025granted Jul 2025Aug 2025Manchester7.2
Manchester Academy, Moss Lane Eastrooftop solarrooftop solar—approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Manchester7.3
Manchester Academy, Moss Lane Eastrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026Manchester7.3
Sainsburys Supermarket, Regent Roadrooftop solarrooftop solar0.3approved, not builtupdated Nov 2025Aug 2025granted Sep 2025Nov 2025Salford7.3
Thg Icon, Sunbank Lane, Unit 2rooftop solarrooftop solar0.8refusedupdated Jul 2025May 2025refused Jul 2025Jul 2025Manchester7.4
Thg Studio, Sunbank Lanerooftop solarrooftop solar0.4refusedupdated Jul 2025May 2025refused Jul 2025Jul 2025Manchester7.4
DHL Express Manchester, Sunbank Lanerooftop solarrooftop solar0.3approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Manchester7.4
Thg Icon, Sunbank Lane -Solar Arrayrooftop solarrooftop solar0.2refusedupdated Jul 2025May 2025refused Jul 2025Jul 2025Manchester7.4
Brunel Avenuerooftop solarrooftop solar0.2application submittedupdated Feb 2026Jan 2026—Feb 2026Salford7.6
Ymca And Castlefield Hotel, Liverpool Roadrooftop solarrooftop solar0.2application withdrawnupdated Feb 2024Dec 2023—Feb 2024Manchester7.7
CSG Cadishead Weee, Liverpool Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Salford7.8
Xaverian College, Lower Park Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Mar 2023granted Apr 2024Apr 2024Manchester7.9
Royal Northern College Of Music, Oxford Roadrooftop solarrooftop solar0.2under constructionupdated Sep 2021Aug 2021granted Jul 2022Sep 2021Manchester7.9
Manchester Marriott Victoria And Albert Hotelrooftop solarrooftop solar0.2abandonedupdated Jul 2024Dec 2023granted Jun 2024Jul 2024Salford8.0
Manchester Royal Infirmary, Oxford Roadrooftop solarrooftop solar—approved, not builtupdated Apr 2026Dec 2025granted Feb 2026Apr 2026Manchester8.0
Styal Roadrooftop solarrooftop solar0.2application submittedMay 2026——Manchester8.4
Weinerberger House, Brooks Driverooftop solarrooftop solar0.1application submittedupdated Nov 2024Sep 2024—Nov 2024Stockport8.4
The Albion Academy, London Streetrooftop solarrooftop solar0.2approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Salford8.8
The Printworks, Withy Groverooftop solarrooftop solar0.2approved, not builtupdated Aug 2025Jun 2025granted Aug 2025Aug 2025Manchester9.1
Mercedes Benz, Heaton Merseyrooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Jun 2023granted Jul 2023Aug 2023Stockport9.7
Jj Food Service, 1A Lamplight Wayrooftop solarrooftop solar0.4approved, not builtupdated Nov 2023Aug 2023granted Nov 2023Nov 2023Salford9.7
Bird Hall Lane, Cheadle Heathrooftop solarrooftop solar0.5approved, not builtupdated May 2026Dec 2025granted Mar 2026May 2026Stockport9.8

2 more projects not listed (furthest or smallest).

Distance from the average position of the M33 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.5
Rooftop solar613481621.4
Battery storage1127111,575

MW in pipeline: pending, approved and under-construction capacity.

How Trafford decides solar, wind and battery applications

ApplicationsTraffordUK
Decided applications (solar, wind, battery)2810,236
Refused6 (21%)19%
Solar refused3 of 1912%
Battery storage refused3 of 916%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

All projects in Trafford

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near M33, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.