Wild Fowl Farm, Carrington Lane (35 MW battery storage)

Wild Fowl Farm, Carrington Lane is a 35 MW battery storage project in Trafford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 February 2025, not yet built; the record was last updated on 4 March 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWbattery storage
approved, not builtstatus in REPD
4 March 2025record last updated
Traffordcouncil area

Planning timeline

DateStage
1 May 2024Application submitted
29 August 2024Refused by the planning authority
17 February 2025Appeal allowed

Project details

Technology
battery storage (stand-alone storage)
Capacity
35 MW
Status (REPD)
approved, not built
Record last updated
4 March 2025
Operator or applicant
O&G Solar (SPV 56) Ltd
Planning authority
Trafford
Planning application reference
113358/FUL/24
Address (REPD)
Wild Fowl Farm Carrington Lane Carrington
Council area (by location)
Trafford
Time to decision
17 weeks
Name in REPD
Wild Fowl Farm, Carrington Lane - Battery Storage Facility
REPD reference
16383

Who decides

ApplicationsTraffordUK
Decided applications (solar, wind, battery)2810,236
Refused6 (21%)19%
Solar refused3 of 1912%
Battery storage refused3 of 916%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Daines Battery Energy Storage Systembattery storage600approved, not built1.5
Carrington Power Station, Manchester Roadbattery storage680under construction2.2
Golf Roadbattery storage90approved, not built5.4
Sale Golf Club, Golf Roadbattery storage70approved, not built5.4
Freshfields, Fairy Lanebattery storage99.9under construction6.0
West Didsbury Battery Storagebattery storage50operational6.1
Whitehead Landfill Site, Lower Green Lane Solar Farmsolar farm10application submitted8.0
Lights Oaks Mosssolar farm5abandoned8.1
Silver Lane, Risley Solar Farmsolar farm5approved, not built8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4331, -2.3697).