Energy Projects Near You

Welkin Mill, Welkin Road (49.9 MW battery storage)

Welkin Mill, Welkin Road is a 49.9 MW battery storage project in Stockport, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 January 2024; the record was last updated on 17 April 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
under constructionstatus in REPD
17 April 2024record last updated
Stockportcouncil area

Planning timeline

DateStage
9 December 2022Application submitted
1 August 2023Planning permission granted
1 January 2024Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
under construction
Record last updated
17 April 2024
Operator or applicant
Noriker Power Limited
Planning authority
Stockport
Planning application reference
DC/087394
Address (REPD)
Welkin Mill, Welkin Road, Bredbury, Stockport
Council area (by location)
Stockport
Time to decision
34 weeks
Name in REPD
Welkin Mill, Welkin Road - Battery Storage
REPD reference
12982

Who decides

ApplicationsStockportUK
Decided applications (solar, wind, battery)2210,236
Refused1 (5%)19%
Solar refused1 of 1412%
Battery storage refused0 of 816%
Median time from submission to decision12.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Welkin Road, Bredburybattery storage20operational0.1
Bredbury Substationbattery storage49.9under construction0.4
Ashton Road, Bredburybattery storage75approved, not built1.4
Goyt Hall Farm, Goyt Valley Footpathbattery storage40approved, not built1.6
Newby Road, Hazel Grovebattery storage7.5approved, not built4.3
Torkington Road, Hazel Grovesolar farm30application submitted5.5
Woodford Roadbattery storage100approved, not built8.1
Holden Waybattery storage6approved, not built8.2
Medlock Road, Failsworthbattery storage30approved, not built8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4172, -2.1364).