Medlock Road, Failsworth (30 MW battery storage)

Medlock Road, Failsworth is a 30 MW battery storage project in Oldham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 October 2025, not yet built; the record was last updated on 10 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWbattery storage
approved, not builtstatus in REPD
10 November 2025record last updated
Oldhamcouncil area

Planning timeline

DateStage
8 October 2024Application submitted
28 April 2025Refused by the planning authority
24 July 2025Appeal lodged
21 October 2025Planning permission granted
21 October 2025Appeal allowed
21 October 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
10 November 2025
Operator or applicant
Root Power (North) Limited
Planning authority
Oldham
Planning application reference
FUL/353405/24
Appeal reference
REFUSE/0249/25
Address (REPD)
South East Side Of Medlock Road Failsworth
Council area (by location)
Oldham
Time to decision
54 weeks
Name in REPD
Medlock Road, Failsworth - Battery Energy Storage
REPD reference
17657

Who decides

ApplicationsOldhamUK
Decided applications (solar, wind, battery)1910,236
Refused2 (11%)19%
Solar refused0 of 1312%
Onshore wind refused1 of 145%
Battery storage refused1 of 516%
Median time from submission to decision9.0 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Chaddertonbattery storage20under construction4.0
Whitegate Battery Storagebattery storage57under construction4.1
Moston Valebattery storage10under construction4.2
Holden Waybattery storage6approved, not built4.8
Lowerfields Farm, Warren Lanebattery storage27application submitted5.1
Printworks Road - Stalybridge Battery Storagebattery storage150approved, not built6.8
Ashton Road, Bredburybattery storage75approved, not built8.1
Welkin Mill, Welkin Roadbattery storage49.9under construction8.9
Welkin Road, Bredburybattery storage20operational9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4968, -2.1463).