Solar, wind and battery projects near Manchester (M35)
85 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of M35 (Oldham): 7 are waiting for a planning decision, 66 approved but not yet running, 7 operational. The largest live scheme is Printworks Road - Stalybridge Battery Storage (150 MW battery storage, approved on 15 December 2023, not yet built), 7.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of M35
Projects of 1 MW and more (18)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Medlock Road, Failsworthbattery storage | battery storage | 30 | approved, not builtupdated Nov 2025 | Oct 2024 | granted Oct 2025 | Nov 2025 | Oldham | 1.3 |
| Chaddertonbattery storage | battery storage | 20 | under constructionupdated May 2022 | Apr 2022 | granted Dec 2022 | May 2022 | Oldham | 2.8 |
| Whitegate Battery Storagebattery storage | battery storage | 57 | under constructionupdated Oct 2025 | Feb 2022 | granted May 2022 | Oct 2025 | Oldham | 2.9 |
| Moston Valebattery storage | battery storage | 10 | under constructionupdated May 2021 | Jul 2020 | granted Nov 2020 | May 2021 | Manchester | 3.5 |
| City Football Academysolar farm | solar farm | 1.1 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Manchester | 3.8 |
| City Football Academy, Ashton New Roadrooftop solar | rooftop solar | 3.4 | operationalupdated Jun 2026 | Mar 2024 | granted Apr 2024 | Jun 2026 | Manchester | 3.8 |
| IGC, Lydia Becker Wayrooftop solar | rooftop solar | 3.1 | approved, not builtupdated Sep 2025 | Aug 2025 | granted Sep 2025 | Sep 2025 | Oldham | 3.9 |
| City of Manchester Stadiumwind turbine | wind turbine | 2 | abandonedupdated Nov 2008 | Sep 2005 | granted Sep 2006 | Nov 2008 | Manchester | 3.9 |
| Chaddertonbattery storage | battery storage | 2.5 | approved, not built may be out of dateupdated Mar 2022 | Mar 2022 | granted May 2022 | Mar 2022 | Oldham | 4.0 |
| Lowerfields Farm, Warren Lanebattery storage | battery storage | 27 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Oldham | 4.8 |
| Robert McBride Ltdrooftop solar | rooftop solar | 1.3 | permission expiredupdated Aug 2018 | Mar 2015 | granted Apr 2015 | Aug 2018 | Rochdale | 5.4 |
| Holden Waybattery storage | battery storage | 6 | approved, not built may be out of dateupdated Jun 2020 | Apr 2017 | granted Jun 2018 | Jun 2020 | Tameside | 5.8 |
| Tesco Distribution Centre, Stakehill Industrial Estaterooftop solar | rooftop solar | 1 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | Rochdale | 6.5 |
| Denton Hall Farm Road, Dentonrooftop solar | rooftop solar | 1.2 | operationalupdated Jan 2022 | Jan 2022 | granted Jul 2023 | Jan 2022 | Tameside | 6.6 |
| Printworks Road - Stalybridge Battery Storagebattery storage | battery storage | 150 | approved, not builtupdated Dec 2023 | Sep 2023 | granted Dec 2023 | Dec 2023 | Tameside | 7.5 |
| Godley Water Treatment Worksfloating solar | floating solar | 3 | operationalupdated Jun 2016 | — | — | Jun 2016 | Tameside | 8.6 |
| Ashton Road, Bredburybattery storage | battery storage | 75 | approved, not builtupdated Aug 2025 | Jan 2025 | granted Jul 2025 | Aug 2025 | Stockport | 9.4 |
| Chamber Housesolar farm | solar farm | 4 | under constructionupdated Oct 2023 | Jun 2020 | granted Aug 2020 | Oct 2023 | Rochdale | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (60)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Land at Wrigley Headsolar farm | solar farm | 0.9 | under constructionupdated Mar 2026 | Mar 2020 | granted Dec 2021 | Mar 2026 | Manchester | 1.0 |
| Reliance Trading Estate,Reliance Streetrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | Manchester | 1.7 |
| Laurus Ryecroft High School, Lumb Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Tameside | 2.2 |
| Middleton Associates, Chaddertonrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2023 | Sep 2023 | granted Oct 2023 | Oct 2023 | Oldham | 2.6 |
| The Sharp Projectrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2021 | Jun 2021 | granted Aug 2021 | Jun 2021 | Manchester | 2.8 |
| Airtech Advanced Materialsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Nov 2025 | Sep 2025 | granted Oct 2025 | Nov 2025 | Oldham | 2.9 |
| Oldham Broadway Business Park, Broadgaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2024 | Dec 2023 | granted Mar 2024 | Apr 2024 | Oldham | 3.1 |
| Central Park Solar photovalticsrooftop solar | rooftop solar | 0.1 | operationalupdated Jul 2021 | Jun 2021 | granted Sep 2021 | Jul 2021 | Manchester | 3.2 |
| The National Cycling Centrerooftop solar | rooftop solar | 0.9 | under constructionupdated Apr 2022 | Apr 2022 | granted Aug 2022 | Apr 2022 | Manchester | 3.4 |
| The National Cycling Centre Velodromerooftop solar | rooftop solar | 0.7 | operationalupdated Mar 2023 | Sep 2020 | granted Oct 2020 | Mar 2023 | Manchester | 3.4 |
| Oldham Broadway Business Park Solar Panelsrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2021 | Feb 2021 | granted Apr 2021 | Mar 2021 | Oldham | 3.6 |
| Burlington Streetrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Jan 2024 | Jan 2024 | Tameside | 3.8 |
| Foxdenton Lane, Chaddertonrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2025 | Dec 2024 | granted Jan 2025 | Jan 2025 | Oldham | 3.9 |
| Duo Plastics Limited, Vickers Streetrooftop solar | rooftop solar | 0.6 | application submittedupdated Nov 2024 | Sep 2024 | — | Nov 2024 | Manchester | 3.9 |
| G H Sheldon, Stainburn Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2023 | May 2023 | granted Jul 2023 | Jul 2023 | Manchester | 3.9 |
| Manchester Communication Academy, Silchester Driverooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2023 | Aug 2023 | granted Sep 2023 | Sep 2023 | Manchester | 4.0 |
| Unit C, Kelbrook Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Manchester | 4.0 |
| Bentfield Industrial Unitsbattery storage | battery storage | 0.3 | approved, not built may be out of dateupdated Jan 2021 | Feb 2020 | granted May 2020 | Jan 2021 | Oldham | 4.0 |
| Etihad Stadium, Ashton New Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Mar 2025 | granted May 2025 | May 2025 | Manchester | 4.1 |
| New Smithfield Market, Whitworth Street East -Solar Panelsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Manchester | 4.2 |
| New Smithfield Marketrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Manchester | 4.2 |
| East Manchester Academy, Grey Mare Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2025 | Aug 2025 | granted Sep 2025 | Sep 2025 | Manchester | 4.3 |
| Ashton Old Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2022 | Apr 2022 | granted Jun 2022 | May 2022 | Manchester | 4.5 |
| Hammerstone Road Depotrooftop solar | rooftop solar | — | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | Manchester | 4.6 |
| Tesco Stores, Featherstall Road Northrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Jul 2023 | Aug 2023 | Oldham | 4.7 |
| Featherstall Road Tesco (Chadderton)rooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2020 | Jan 2020 | granted Mar 2020 | Mar 2020 | Oldham | 4.7 |
| Sainsburys Supermarkets, Union Streetrooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2026 | Feb 2026 | granted Apr 2026 | May 2026 | Oldham | 4.7 |
| Manor Mill, Victoria Streetrooftop solar | rooftop solar | 0.5 | approved, not built may be out of dateupdated Dec 2022 | Aug 2022 | granted Dec 2022 | Dec 2022 | Oldham | 4.8 |
| Riverside Works, Collyhurst Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2026 | Jan 2026 | granted Feb 2026 | Apr 2026 | Manchester | 4.9 |
| Outer Space Studios Solar Panelsrooftop solar | rooftop solar | 0.6 | operationalupdated Jan 2022 | Jun 2021 | granted Nov 2021 | Jan 2022 | Manchester | 5.1 |
| Tesco Super-Store (Garratt Way, Gorton)rooftop solar | rooftop solar | 0.7 | operationalupdated Jul 2020 | Jan 2019 | granted Mar 2019 | Jul 2020 | Manchester | 5.2 |
| Co Op Academy Belle Vue, Hyde Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2026 | Jan 2026 | granted Feb 2026 | Apr 2026 | Manchester | 5.4 |
| Tameside College, Beaufort Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Tameside | 5.4 |
| Tudor Industrial Estate, Ashton Street- Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Oct 2025 | Jun 2025 | granted Sep 2025 | Oct 2025 | Tameside | 5.4 |
| The West Side Of Hanson Street, Middletonbattery storage | battery storage | 0.2 | application submitted may be out of dateupdated Feb 2023 | Feb 2023 | — | Feb 2023 | Rochdale | 5.5 |
| Oldham Athletic Football Club, Hilbre Avenuerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Nov 2025 | Sep 2025 | granted Oct 2025 | Nov 2025 | Oldham | 5.5 |
| Molnlycke Healthcare, Brook Streetrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2023 | Feb 2023 | granted Mar 2023 | Apr 2023 | Oldham | 5.6 |
| Tameside General Hospital, Fountain Streetrooftop solar | rooftop solar | 0.3 | application submitted | Jun 2026 | — | — | Tameside | 5.8 |
| The Printworks, Withy Groverooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Aug 2025 | Aug 2025 | Manchester | 6.2 |
| Sainsburys Supermarkets, Heaton Park Roadrooftop solar | rooftop solar | 0.3 | application submitted | May 2026 | — | — | Manchester | 6.4 |
| Tame Box, Tame Streetbattery storage | battery storage | 0.2 | approved, not built may be out of dateupdated Nov 2022 | Sep 2022 | granted Oct 2022 | Nov 2022 | Tameside | 6.4 |
| Gorton Education Village, Wembley Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Dec 2025 | Oct 2025 | granted Nov 2025 | Dec 2025 | Manchester | 6.4 |
| Morrisons Superstore, Saxon Streetrooftop solar | rooftop solar | 0.5 | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 | Tameside | 6.4 |
| Cardinal Langley RC High School, Rochdale Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Nov 2025 | Jul 2025 | granted Sep 2025 | Nov 2025 | Rochdale | 6.6 |
| Concordiarooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Jan 2024 | Jan 2024 | Tameside | 6.8 |
| Royal Northern College Of Music, Oxford Roadrooftop solar | rooftop solar | 0.2 | under constructionupdated Sep 2021 | Aug 2021 | granted Jul 2022 | Sep 2021 | Manchester | 6.9 |
| Manchester Royal Infirmary, Oxford Roadrooftop solar | rooftop solar | — | approved, not builtupdated Apr 2026 | Dec 2025 | granted Feb 2026 | Apr 2026 | Manchester | 6.9 |
| Broughton Hub, Rigby Streetrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2024 | Sep 2024 | granted Nov 2024 | Nov 2024 | Salford | 6.9 |
| Hopwood Hall College, Rochdale Roadrooftop solar | rooftop solar | 0.5 | application submittedupdated Sep 2024 | Aug 2024 | — | Sep 2024 | Rochdale | 7.2 |
| Xaverian College, Lower Park Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2024 | Mar 2023 | granted Apr 2024 | Apr 2024 | Manchester | 7.3 |
| David Lloyd Health Club, Heywood Old Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Dec 2023 | Aug 2023 | granted Nov 2023 | Dec 2023 | Rochdale | 7.4 |
| Manchester Marriott Victoria And Albert Hotelrooftop solar | rooftop solar | 0.2 | abandonedupdated Jul 2024 | Dec 2023 | granted Jun 2024 | Jul 2024 | Salford | 7.4 |
| Ymca And Castlefield Hotel, Liverpool Roadrooftop solar | rooftop solar | 0.2 | application withdrawnupdated Feb 2024 | Dec 2023 | — | Feb 2024 | Manchester | 7.6 |
| Manchester Academy, Moss Lane Eastrooftop solar | rooftop solar | — | approved, not builtupdated Aug 2023 | Jul 2023 | granted Aug 2023 | Aug 2023 | Manchester | 7.6 |
| Manchester Academy, Moss Lane Eastrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Nov 2025 | granted Dec 2025 | Jan 2026 | Manchester | 7.6 |
| Manchester Metropolitan University, Birley Fieldsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | Manchester | 7.7 |
| Sheffield Roadbattery storage | battery storage | — | approved, not built may be out of dateupdated Mar 2022 | Feb 2022 | granted Sep 2022 | Mar 2022 | Tameside | 8.1 |
| Morrisons Superstore, Mottram Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2025 | Oct 2025 | granted Nov 2025 | Dec 2025 | Tameside | 8.1 |
| Sainsburys Supermarket, Regent Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Nov 2025 | Aug 2025 | granted Sep 2025 | Nov 2025 | Salford | 8.2 |
| Loreto College, Chichester Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Nov 2025 | Aug 2025 | granted Oct 2025 | Nov 2025 | Manchester | 8.2 |
7 more projects not listed (furthest or smallest).
Distance from the average position of the M35 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 3 | 0 | 3 | 0 | 0 | 6 |
| Rooftop solar | 65 | 5 | 51 | 6 | 0 | 21.3 |
| Floating solar | 1 | 0 | 0 | 1 | 0 | 0 |
| Wind turbine | 1 | 0 | 0 | 0 | 0 | 0 |
| Battery storage | 15 | 2 | 12 | 0 | 0 | 378 |
MW in pipeline: pending, approved and under-construction capacity.
How Oldham decides solar, wind and battery applications
| Applications | Oldham | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 19 | 10,236 |
| Refused | 2 (11%) | 19% |
| Solar refused | 0 of 13 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 9.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near M35, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.