Printworks Road - Stalybridge Battery Storage (150 MW)

Printworks Road - Stalybridge Battery Storage is a 150 MW battery storage project in Tameside, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 December 2023, not yet built; the record was last updated on 19 December 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

150 MWbattery storage
approved, not builtstatus in REPD
19 December 2023record last updated
Tamesidecouncil area

Planning timeline

DateStage
11 September 2023Application submitted
15 December 2023Planning permission granted
15 December 2026Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
150 MW
Status (REPD)
approved, not built
Record last updated
19 December 2023
Operator or applicant
Zenobe Energy
Planning authority
Tameside
Planning application reference
23/00770/FUL
Address (REPD)
South Of Stalybridge Substation Printworks Road Stalybridge
Council area (by location)
Tameside
Time to decision
14 weeks
REPD reference
10808

Who decides

ApplicationsTamesideUK
Decided applications (solar, wind, battery)1210,236
Refused0 (0%)19%
Solar refused0 of 712%
Battery storage refused0 of 516%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Holden Waybattery storage6approved, not built2.7
Lowerfields Farm, Warren Lanebattery storage27application submitted5.1
Medlock Road, Failsworthbattery storage30approved, not built6.8
Chaddertonbattery storage20under construction9.1
Whitegate Battery Storagebattery storage57under construction9.1
Ashton Road, Bredburybattery storage75approved, not built9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4945, -2.0434).