Energy Projects Near You

Whitegate Battery Storage (57 MW)

Whitegate Battery Storage is a 57 MW battery storage project in Oldham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 October 2023; the record was last updated on 14 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

57 MWbattery storage
under constructionstatus in REPD
14 October 2025record last updated
Oldhamcouncil area

Planning timeline

DateStage
14 February 2022Application submitted
19 May 2022Planning permission granted
1 October 2023Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
57 MW
Status (REPD)
under construction
Record last updated
14 October 2025
Operator or applicant
Pelagic Energy (Constantine Energy)
Planning authority
Oldham
Planning application reference
FUL/348501/22
Address (REPD)
The National Grid Station, Broadgate, Chadderton, Oldham
Council area (by location)
Oldham
Time to decision
13 weeks
REPD reference
10690

Who decides

ApplicationsOldhamUK
Decided applications (solar, wind, battery)1910,236
Refused2 (11%)19%
Solar refused0 of 1312%
Onshore wind refused1 of 145%
Battery storage refused1 of 516%
Median time from submission to decision9.0 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Chaddertonbattery storage20under construction0.1
Moston Valebattery storage10under construction4.1
Medlock Road, Failsworthbattery storage30approved, not built4.1
Lowerfields Farm, Warren Lanebattery storage27application submitted4.9
Astra Centre, Royal Barn Roadbattery storage40under construction7.2
Gipsy Lanebattery storage20under construction7.3
Holden Waybattery storage6approved, not built8.0
Ellenroad Farm, Bentgate Streetbattery storage30approved, not built8.4
Miall Power Energy Storage Facilitybattery storage5refused8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5322, -2.1658).