Energy Projects Near You

Holden Way (6 MW battery storage)

Holden Way is a 6 MW battery storage project in Tameside, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 June 2018, not yet built; the record was last updated on 4 June 2020. REPD also records that the planning permission expired on 25 June 2021, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWbattery storage
approved, not builtmay be out of datestatus in REPD
4 June 2020record last updated
Tamesidecouncil area

REPD also records that the planning permission expired on 25 June 2021, so the project may not go ahead in this form.

Planning timeline

DateStage
10 April 2017Application submitted
25 June 2018Planning permission granted
25 June 2021Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
6 MW
Status (REPD)
approved, not built
Record last updated
4 June 2020
Operator or applicant
STOR Power
Planning authority
Tameside
Planning application reference
17/00846/FUL
Address (REPD)
Land Off Holden Way, Dukinfield, Greater Manchester
Council area (by location)
Tameside
Time to decision
63 weeks
REPD reference
7145

Who decides

ApplicationsTamesideUK
Decided applications (solar, wind, battery)1210,236
Refused0 (0%)19%
Solar refused0 of 712%
Battery storage refused0 of 516%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Printworks Road - Stalybridge Battery Storagebattery storage150approved, not built2.7
Medlock Road, Failsworthbattery storage30approved, not built4.8
Lowerfields Farm, Warren Lanebattery storage27application submitted5.4
Ashton Road, Bredburybattery storage75approved, not built6.9
Chaddertonbattery storage20under construction8.0
Whitegate Battery Storagebattery storage57under construction8.0
Welkin Mill, Welkin Roadbattery storage49.9under construction8.2
Welkin Road, Bredburybattery storage20operational8.3
Bredbury Substationbattery storage49.9under construction8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4822, -2.0779).