Ashton Road, Bredbury (75 MW battery storage)
Ashton Road, Bredbury is a 75 MW battery storage project in Stockport, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 July 2025, not yet built; the record was last updated on 5 August 2025.
75 MWbattery storage
approved, not builtstatus in REPD
5 August 2025record last updated
Stockportcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 6 January 2025 | Application submitted |
| 24 July 2025 | Planning permission granted |
| 24 July 2028 | Permission due to expire (unless work starts) |
Project details
- Technology
- battery storage (stand-alone storage)
- Capacity
- 75 MW
- Status (REPD)
- approved, not built
- Record last updated
- 5 August 2025
- Operator or applicant
- Cragside Energy Limited
- Planning authority
- Stockport
- Planning application reference
- DC/094002
- Address (REPD)
- West Of Ashton Road Bredbury
- Council area (by location)
- Stockport
- Time to decision
- 28 weeks
- Name in REPD
- Ashton Road, Bredbury - Battery Energy Storage
- REPD reference
- 16667
Who decides
| Applications | Stockport | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 22 | 10,236 |
| Refused | 1 (5%) | 19% |
| Solar refused | 1 of 14 | 12% |
| Battery storage refused | 0 of 8 | 16% |
| Median time from submission to decision | 12.8 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Welkin Mill, Welkin Road | battery storage | 49.9 | under construction | 1.4 |
| Welkin Road, Bredbury | battery storage | 20 | operational | 1.5 |
| Bredbury Substation | battery storage | 49.9 | under construction | 1.6 |
| Goyt Hall Farm, Goyt Valley Footpath | battery storage | 40 | approved, not built | 2.0 |
| Newby Road, Hazel Grove | battery storage | 7.5 | approved, not built | 5.2 |
| Torkington Road, Hazel Grove | solar farm | 30 | application submitted | 5.7 |
| Holden Way | battery storage | 6 | approved, not built | 6.9 |
| Medlock Road, Failsworth | battery storage | 30 | approved, not built | 8.1 |
| Woodford Road | battery storage | 100 | approved, not built | 9.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4256, -2.1207).