Energy Projects Near You

Goyt Hall Farm, Goyt Valley Footpath (40 MW battery storage)

Goyt Hall Farm, Goyt Valley Footpath is a 40 MW battery storage project in Stockport, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 August 2024, not yet built; the record was last updated on 9 September 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWbattery storage
approved, not builtstatus in REPD
9 September 2024record last updated
Stockportcouncil area

Planning timeline

DateStage
1 December 2023Application submitted
23 August 2024Planning permission granted
23 August 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
9 September 2024
Operator or applicant
Queequeg Renewables Limited
Planning authority
Stockport
Planning application reference
DC/090340
Address (REPD)
Goyt Hall Farm Goyt Valley Footpath Bredbury Stockport
Council area (by location)
Stockport
Time to decision
38 weeks
Name in REPD
Goyt Hall Farm, Goyt Valley Footpath - Battery Energy Storage
REPD reference
13985

Who decides

ApplicationsStockportUK
Decided applications (solar, wind, battery)2210,236
Refused1 (5%)19%
Solar refused1 of 1412%
Battery storage refused0 of 816%
Median time from submission to decision12.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bredbury Substationbattery storage49.9under construction1.3
Welkin Road, Bredburybattery storage20operational1.5
Welkin Mill, Welkin Roadbattery storage49.9under construction1.6
Ashton Road, Bredburybattery storage75approved, not built2.0
Newby Road, Hazel Grovebattery storage7.5approved, not built3.4
Torkington Road, Hazel Grovesolar farm30application submitted3.9
Woodford Roadbattery storage100approved, not built7.4
Holden Waybattery storage6approved, not built8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4081, -2.1172).