Energy Projects Near You

Bredbury Substation (49.9 MW battery storage)

Bredbury Substation is a 49.9 MW battery storage project in Stockport, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 March 2023; the record was last updated on 20 September 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
under constructionstatus in REPD
20 September 2021record last updated
Stockportcouncil area

Planning timeline

DateStage
10 September 2021Application submitted
2 December 2021Planning permission granted
1 March 2023Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
under construction
Record last updated
20 September 2021
Operator or applicant
Private Developer
Planning authority
Stockport
Planning application reference
DC/082085
Address (REPD)
Bredbury Substation, Stockport Road West, Bredbury, Stockport
Council area (by location)
Stockport
Time to decision
12 weeks
Name in REPD
Bredbury Substation - Battery Storage Facility
REPD reference
9653

Who decides

ApplicationsStockportUK
Decided applications (solar, wind, battery)2210,236
Refused1 (5%)19%
Solar refused1 of 1412%
Battery storage refused0 of 816%
Median time from submission to decision12.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Welkin Road, Bredburybattery storage20operational0.3
Welkin Mill, Welkin Roadbattery storage49.9under construction0.4
Goyt Hall Farm, Goyt Valley Footpathbattery storage40approved, not built1.3
Ashton Road, Bredburybattery storage75approved, not built1.6
Newby Road, Hazel Grovebattery storage7.5approved, not built3.9
Torkington Road, Hazel Grovesolar farm30application submitted5.1
Woodford Roadbattery storage100approved, not built7.7
Holden Waybattery storage6approved, not built8.5
Medlock Road, Failsworthbattery storage30approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4138, -2.1339).