Energy Projects Near You

Solar, wind and battery projects near Stockport (SK4)

96 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SK4 (Stockport): 6 are waiting for a planning decision, 73 approved but not yet running, 10 operational. The largest live scheme is Woodford Road (100 MW battery storage, approved on 30 May 2025, not yet built), 8.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

96projects within 10 km
6awaiting a decision
73approved, not running
10operational

Projects within 10 km of SK4

Projects of 1 MW and more (22)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Tesco Burnage Storerooftop solarrooftop solar1approved, not builtupdated Jun 2020Nov 2019granted Jan 2020Jun 2020Manchester1.9
Tesco Store East Didsburyrooftop solarrooftop solar1approved, not builtupdated Feb 2021Nov 2019granted Jan 2020Feb 2021Manchester2.6
Welkin Mill, Welkin Roadbattery storagebattery storage49.9under constructionupdated Apr 2024Dec 2022granted Aug 2023Apr 2024Stockport3.0
Welkin Road, Bredburybattery storagebattery storage20operationalupdated Jan 2026Dec 2020granted Jan 2021Jan 2026Stockport3.1
Bredbury Substationbattery storagebattery storage49.9under constructionupdated Sep 2021Sep 2021granted Dec 2021Sep 2021Stockport3.2
Ashton Road, Bredburybattery storagebattery storage75approved, not builtupdated Aug 2025Jan 2025granted Jul 2025Aug 2025Stockport4.1
Goyt Hall Farm, Goyt Valley Footpathbattery storagebattery storage40approved, not builtupdated Sep 2024Dec 2023granted Aug 2024Sep 2024Stockport4.5
Denton Hall Farm Road, Dentonrooftop solarrooftop solar1.2operationalupdated Jan 2022Jan 2022granted Jul 2023Jan 2022Tameside4.6
Newby Road, Hazel Grovebattery storagebattery storage7.5approved, not built may be out of dateupdated May 2022Apr 2022granted Nov 2022May 2022Stockport5.7
West Didsbury Battery Storagebattery storagebattery storage50operationalupdated Nov 2023Sep 2017granted Nov 2019Nov 2023Trafford6.6
Freshfields, Fairy Lanebattery storagebattery storage99.9under constructionupdated Jan 2026Oct 2022granted Mar 2023Jan 2026Trafford6.6
City Football Academy, Ashton New Roadrooftop solarrooftop solar3.4operationalupdated Jun 2026Mar 2024granted Apr 2024Jun 2026Manchester6.9
City Football Academysolar farmsolar farm1.1approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Manchester6.9
Golf Roadbattery storagebattery storage90approved, not builtupdated Oct 2024Jun 2023granted Oct 2024Oct 2024Trafford7.2
Sale Golf Club, Golf Roadbattery storagebattery storage70approved, not builtupdated Nov 2023Apr 2023granted Nov 2023Nov 2023Trafford7.2
City of Manchester Stadiumwind turbinewind turbine2abandonedupdated Nov 2008Sep 2005granted Sep 2006Nov 2008Manchester7.6
Torkington Road, Hazel Grovesolar farmsolar farm30application submittedupdated Aug 2025Jun 2025—Aug 2025Stockport7.9
Woodford Roadbattery storagebattery storage100approved, not builtupdated Jul 2025Dec 2024granted May 2025Jul 2025Stockport8.4
Medlock Road, Failsworthbattery storagebattery storage30approved, not builtupdated Nov 2025Oct 2024granted Oct 2025Nov 2025Oldham8.9
Godley Water Treatment Worksfloating solarfloating solar3operationalupdated Jun 2016——Jun 2016Tameside9.1
Moston Valebattery storagebattery storage10under constructionupdated May 2021Jul 2020granted Nov 2020May 2021Manchester9.7
Holden Waybattery storagebattery storage6approved, not built may be out of dateupdated Jun 2020Apr 2017granted Jun 2018Jun 2020Tameside9.8
Smaller schemes under 1 MW, mostly rooftop solar (60)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
A G Parfett and Son, Didsbury Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2023Apr 2023granted May 2023May 2023Stockport1.0
Heaton Norris Solar PV Panelrooftop solarrooftop solar0.2approved, not builtupdated May 2022May 2022granted Aug 2022May 2022Stockport1.1
Mercedes Benz, Heaton Merseyrooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Jun 2023granted Jul 2023Aug 2023Stockport1.2
Decathlon, Georges Roadrooftop solarrooftop solar0.1approved, not builtupdated Apr 2024Mar 2024granted Apr 2024Apr 2024Stockport1.2
Audi Stockport, Brinksway, Edgeleyrooftop solarrooftop solar0.3operationalupdated May 2022May 2022granted Oct 2023May 2022Stockport1.6
Herrod Avenue, South Reddishbattery storagebattery storage—application withdrawnupdated Jun 2024Dec 2023—Jun 2024Stockport1.7
Life Leisure Grand Central, Grand Central Squarerooftop solarrooftop solar0.2approved, not builtupdated Jan 2023Sep 2022granted Dec 2022Jan 2023Stockport2.0
Bird Hall Lane, Cheadle Heathrooftop solarrooftop solar0.5approved, not builtupdated May 2026Dec 2025granted Mar 2026May 2026Stockport2.6
Rrg Toyota, St Marys Wayrooftop solarrooftop solar0.2approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025Stockport2.7
Hercules Office Park, Bird Hall Lane Solar Arraysrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Stockport3.0
Scotscroft Towers Business Park, Wilmslow Roadrooftop solarrooftop solar0.1approved, not built may be out of dateupdated Feb 2024Jan 2024granted Feb 2024Feb 2024Manchester3.2
Gorton Education Village, Wembley Roadrooftop solarrooftop solar0.6approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Manchester3.5
Adswood Roadbattery storagebattery storage—approved, not builtupdated Sep 2025Jan 2025granted Aug 2025Sep 2025Stockport3.8
Tesco Super-Store (Garratt Way, Gorton)rooftop solarrooftop solar0.7operationalupdated Jul 2020Jan 2019granted Mar 2019Jul 2020Manchester4.8
Xaverian College, Lower Park Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Mar 2023granted Apr 2024Apr 2024Manchester4.8
Co Op Academy Belle Vue, Hyde Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Jan 2026granted Feb 2026Apr 2026Manchester4.9
Whalley Range High School, Wilbraham Roadrooftop solarrooftop solar0.4approved, not builtupdated Oct 2025Aug 2025granted Sep 2025Oct 2025Manchester5.0
The Adidas Centre, Hazel Groverooftop solarrooftop solar0.6approved, not builtupdated Feb 2023Sep 2022granted Feb 2023Feb 2023Stockport5.3
Weinerberger House, Brooks Driverooftop solarrooftop solar0.1application submittedupdated Nov 2024Sep 2024—Nov 2024Stockport5.4
Hammerstone Road Depotrooftop solarrooftop solar—approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Manchester5.4
Sainsburys, London Roadrooftop solarrooftop solar0.5approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Stockport5.5
Manchester Academy, Moss Lane Eastrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026Manchester5.5
Manchester Academy, Moss Lane Eastrooftop solarrooftop solar—approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Manchester5.5
Outer Space Studios Solar Panelsrooftop solarrooftop solar0.6operationalupdated Jan 2022Jun 2021granted Nov 2021Jan 2022Manchester5.7
Manchester Royal Infirmary, Oxford Roadrooftop solarrooftop solar—approved, not builtupdated Apr 2026Dec 2025granted Feb 2026Apr 2026Manchester5.7
Cheadle Hulme School, Claremont Roadrooftop solarrooftop solar0.3approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Stockport5.7
New Smithfield Market, Whitworth Street East -Solar Panelsrooftop solarrooftop solar0.3approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Manchester5.8
New Smithfield Marketrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Manchester5.8
Ashton Old Roadrooftop solarrooftop solar0.4approved, not builtupdated May 2022Apr 2022granted Jun 2022May 2022Manchester5.9
Morrisons Superstore, Saxon Streetrooftop solarrooftop solar0.5approved, not builtupdated May 2024Mar 2024granted May 2024May 2024Tameside6.1
Bramhall High School, Seal Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Stockport6.2
Unit C, Kelbrook Roadrooftop solarrooftop solar0.6approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023Manchester6.3
The Windrush Millenium Centre, Alexandra Roadrooftop solarrooftop solar—approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Manchester6.3
G H Sheldon, Stainburn Roadrooftop solarrooftop solar0.3approved, not builtupdated Jul 2023May 2023granted Jul 2023Jul 2023Manchester6.4
Royal Northern College Of Music, Oxford Roadrooftop solarrooftop solar0.2under constructionupdated Sep 2021Aug 2021granted Jul 2022Sep 2021Manchester6.6
East Manchester Academy, Grey Mare Lanerooftop solarrooftop solar0.2approved, not builtupdated Sep 2025Aug 2025granted Sep 2025Sep 2025Manchester6.6
Loreto College, Chichester Roadrooftop solarrooftop solar0.4approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Manchester6.7
Manchester Metropolitan University, Birley Fieldsrooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Manchester6.8
Styal Roadrooftop solarrooftop solar0.2application submittedMay 2026——Manchester7.0
Etihad Stadium, Ashton New Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2025Mar 2025granted May 2025May 2025Manchester7.3
The National Cycling Centrerooftop solarrooftop solar0.9under constructionupdated Apr 2022Apr 2022granted Aug 2022Apr 2022Manchester7.3
The National Cycling Centre Velodromerooftop solarrooftop solar0.7operationalupdated Mar 2023Sep 2020granted Oct 2020Mar 2023Manchester7.4
Concordiarooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024Tameside7.5
Pets At Home, Epsom Avenuerooftop solarrooftop solar0.2application submittedupdated Mar 2026Feb 2026—Mar 2026Cheshire East7.7
Tudor Industrial Estate, Ashton Street- Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Oct 2025Jun 2025granted Sep 2025Oct 2025Tameside7.7
Timpson Roadrooftop solarrooftop solar0.5approved, not builtupdated Apr 2022Apr 2022granted May 2022Apr 2022Manchester7.8
Dixons Brooklands Academy, Moor Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Manchester7.8
Metrolink Trafford Depot, Warwick Road Solar Arraysrooftop solarrooftop solar0.3approved, not builtupdated Feb 2022Jan 2022granted Mar 2022Feb 2022Trafford7.9
Metrolink Trafford Depot Solar Panels & Battery Storagerooftop solarrooftop solar0.3refusedupdated Dec 2021May 2021refused Jul 2021Dec 2021Trafford7.9
Metrolink Trafford Depot Solar Panels & Battery Storagebattery storagebattery storage—refusedupdated Dec 2021May 2021refused Jul 2021Dec 2021Trafford7.9
Morrisons Superstore, Mottram Roadrooftop solarrooftop solar0.5approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Tameside8.0
Ymca And Castlefield Hotel, Liverpool Roadrooftop solarrooftop solar0.2application withdrawnupdated Feb 2024Dec 2023—Feb 2024Manchester8.1
Longford Park School, Cromwell Roadrooftop solarrooftop solar0.4approved, not builtupdated Dec 2022Nov 2022granted Dec 2022Dec 2022Trafford8.1
Acute Building, Southmoor Roadrooftop solarrooftop solar0.5approved, not builtupdated Mar 2026Nov 2025granted Jan 2026Mar 2026Manchester8.2
Wythenshawe Hospitalrooftop solarrooftop solar0.6application withdrawnupdated Feb 2022Jan 2022—Feb 2022Manchester8.2
Wythenshawe Hospitalrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Mar 2022Mar 2022granted May 2022Mar 2022Manchester8.2
Endress & Hauser, Floats Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Manchester8.2
The Printworks, Withy Groverooftop solarrooftop solar0.2approved, not builtupdated Aug 2025Jun 2025granted Aug 2025Aug 2025Manchester8.3
Manchester Marriott Victoria And Albert Hotelrooftop solarrooftop solar0.2abandonedupdated Jul 2024Dec 2023granted Jun 2024Jul 2024Salford8.3
Duo Plastics Limited, Vickers Streetrooftop solarrooftop solar0.6application submittedupdated Nov 2024Sep 2024—Nov 2024Manchester8.4

14 more projects not listed (furthest or smallest).

Distance from the average position of the SK4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm2110031.1
Rooftop solar725567120.1
Floating solar100100
Wind turbine100000
Battery storage2001621629

MW in pipeline: pending, approved and under-construction capacity.

How Stockport decides solar, wind and battery applications

ApplicationsStockportUK
Decided applications (solar, wind, battery)2210,236
Refused1 (5%)19%
Solar refused1 of 1412%
Battery storage refused0 of 816%
Median time from submission to decision12.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Stockport

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SK4, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.