Gipsy Lane (20 MW battery storage)

Gipsy Lane is a 20 MW battery storage project in Rochdale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 July 2021; the record was last updated on 1 July 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
under constructionstatus in REPD
1 July 2021record last updated
Rochdalecouncil area

Planning timeline

DateStage
5 November 2019Application submitted
16 March 2020Planning permission granted
1 July 2021Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
under construction
Record last updated
1 July 2021
Operator or applicant
Arlington Energy
Planning authority
Rochdale
Planning application reference
19/01147/FUL
Address (REPD)
Land Rear Of The Royal Toby Ho, Manchester Road, Rochdale
Council area (by location)
Rochdale
Time to decision
19 weeks
REPD reference
7632

Who decides

ApplicationsRochdaleUK
Decided applications (solar, wind, battery)2610,236
Refused4 (15%)19%
Solar refused0 of 1412%
Onshore wind refused3 of 645%
Battery storage refused1 of 616%
Median time from submission to decision10.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Astra Centre, Royal Barn Roadbattery storage40under construction0.1
Miall Power Energy Storage Facilitybattery storage5refused2.3
The Rake, Lower Jowkin Lanebattery storage57approved, not built3.4
Ellenroad Farm, Bentgate Streetbattery storage30approved, not built4.6
Rooley Moorwind farm39.6appeal withdrawn6.7
Whitegate Battery Storagebattery storage57under construction7.3
Great Hill Wind Farmwind farm10.1refused7.4
Chaddertonbattery storage20under construction7.4
Lascar Worksbattery storage20operational7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5977, -2.1786).