Rooley Moor (39.6 MW wind farm)

Rooley Moor is a 39.6 MW wind farm project in Rochdale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 4 January 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

39.6 MWwind farm
appeal withdrawnstatus in REPD
4 January 2016record last updated
Rochdalecouncil area

Planning timeline

DateStage
29 August 2014Application submitted
2 July 2015Refused by the planning authority
26 August 2015Appeal lodged
22 December 2015Appeal withdrawn

Project details

Technology
wind farm
Capacity
39.6 MW
Status (REPD)
appeal withdrawn
Record last updated
4 January 2016
Operator or applicant
Coronation Power
Planning authority
Rochdale
Planning application reference
14/00877/FUL
Appeal reference
APP/P4225/W/15/3129583
Turbines
12
Address (REPD)
Land To The East And West Of Rooley Moor Road Rochdale
Council area (by location)
Rochdale
Time to decision
44 weeks
REPD reference
4614

Who decides

ApplicationsRochdaleUK
Decided applications (solar, wind, battery)2610,236
Refused4 (15%)19%
Solar refused0 of 1412%
Onshore wind refused3 of 645%
Battery storage refused1 of 616%
Median time from submission to decision10.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
The Rake, Lower Jowkin Lanebattery storage57approved, not built4.0
Scout Moor Windfarmwind farm65operational4.1
Scout Moor Windfarm (extension)wind farm36.8refused4.1
Park Road Battery Storagebattery storage10approved, not built4.5
Hogshead Wind Farmwind farm7.1refused5.5
Reaps Moss Wind Farmwind farm10.2operational5.8
Todmorden Moorwind farm12.3operational6.1
Gorpley Wind Farmwind farm9.2appeal withdrawn6.2
Rochdale Road, Edenfieldbattery storage85refused6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6548, -2.211).