The Rake, Lower Jowkin Lane (57 MW battery storage)

The Rake, Lower Jowkin Lane is a 57 MW battery storage project in Rochdale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 April 2024, not yet built; the record was last updated on 13 May 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

57 MWbattery storage
approved, not builtstatus in REPD
13 May 2024record last updated
Rochdalecouncil area

Planning timeline

DateStage
25 July 2023Application submitted
30 April 2024Planning permission granted
30 April 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
57 MW
Status (REPD)
approved, not built
Record last updated
13 May 2024
Operator or applicant
Shaw-Energi Limited
Planning authority
Rochdale
Planning application reference
23/00816/FUL
Address (REPD)
The Rake, Lower Jowkin Lane & Furbarn Road, Rochdale
Council area (by location)
Rochdale
Time to decision
40 weeks
Name in REPD
The Rake, Lower Jowkin Lane - Battery Energy Storage
REPD reference
14597

Earlier applications for this site

ApplicationMWSubmittedOutcome
Waterloo Farm, Furbarn Road 22/00946/FUL571 September 2022withdrawn 3 December 2022

Who decides

ApplicationsRochdaleUK
Decided applications (solar, wind, battery)2610,236
Refused4 (15%)19%
Solar refused0 of 1412%
Onshore wind refused3 of 645%
Battery storage refused1 of 616%
Median time from submission to decision10.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Gipsy Lanebattery storage20under construction3.4
Astra Centre, Royal Barn Roadbattery storage40under construction3.5
Rooley Moorwind farm39.6appeal withdrawn4.0
Miall Power Energy Storage Facilitybattery storage5refused4.4
Lascar Worksbattery storage20operational5.7
Scout Moor Windfarmwind farm65operational6.5
Scout Moor Windfarm (extension)wind farm36.8refused6.5
Ellenroad Farm, Bentgate Streetbattery storage30approved, not built7.4
Rochdale Road, Edenfieldbattery storage85refused7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6192, -2.216).