Lascar Works (20 MW battery storage)

Lascar Works is a 20 MW battery storage project in Bury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 June 2019; the record was last updated on 3 July 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
operationalstatus in REPD
3 July 2019record last updated
Burycouncil area

Planning timeline

DateStage
30 November 2017Application submitted
23 May 2018Planning permission granted
26 March 2019Construction started
26 June 2019Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
operational
Record last updated
3 July 2019
Operator or applicant
Anesco
Planning authority
Bury
Planning application reference
62215
Address (REPD)
Lascar Works, Tanpits Road, Bury, BL9 5BY
Council area (by location)
Bury
Time to decision
25 weeks
REPD reference
7464

Who decides

Bury has 5 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
The Rake, Lower Jowkin Lanebattery storage57approved, not built5.7
Shore Top Farm, Kearsley Roadbattery storage11approved, not built6.5
Stonecloughbattery storage7approved, not built6.9
Astra Centre, Royal Barn Roadbattery storage40under construction7.7
Gipsy Lanebattery storage20under construction7.7
Rochdale Road, Edenfieldbattery storage85refused7.8
Scout Moor Windfarm (extension)wind farm36.8refused8.1
Scout Moor Windfarmwind farm65operational8.1
Rooley Moorwind farm39.6appeal withdrawn8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5975, -2.2951).