Energy Projects Near You

Stoneclough (7 MW battery storage)

Stoneclough is a 7 MW battery storage project in Bolton, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 October 2022, not yet built; the record was last updated on 9 May 2022. REPD also records that the planning permission expired on 24 October 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWbattery storage
approved, not builtmay be out of datestatus in REPD
9 May 2022record last updated
Boltoncouncil area

REPD also records that the planning permission expired on 24 October 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
11 April 2022Application submitted
24 October 2022Planning permission granted
24 October 2025Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
7 MW
Status (REPD)
approved, not built
Record last updated
9 May 2022
Operator or applicant
GAM Capital Limited / Infinis Energy Services Limited
Planning authority
Bolton
Planning application reference
13256/22
Address (REPD)
R/O Shoreside Stables, Prestolee Road, Stoneclough, Manchester
Council area (by location)
Bolton
Time to decision
28 weeks
Name in REPD
Stoneclough - Battery Energy Storage
REPD reference
11161

Who decides

ApplicationsBoltonUK
Decided applications (solar, wind, battery)2210,236
Refused4 (18%)19%
Solar refused1 of 1512%
Onshore wind refused1 of 145%
Battery storage refused2 of 616%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Shore Top Farm, Kearsley Roadbattery storage11approved, not built0.5
Bent Spur Solar Farmsolar farm5operational2.1
Cleworth Hall Farmsolar farm5abandoned6.6
Lascar Worksbattery storage20operational6.9
Whitehead Landfill Site, Lower Green Lane Solar Farmsolar farm10application submitted9.2
Athertonbattery storage30operational10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5477, -2.3568).