Energy Projects Near You

Solar, wind and battery projects near Bury (BL9)

44 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BL9 (Bury): 3 are waiting for a planning decision, 29 approved but not yet running, 4 operational. The largest live scheme is The Rake, Lower Jowkin Lane (57 MW battery storage, approved on 30 April 2024, not yet built), 5.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

44projects within 10 km
3awaiting a decision
29approved, not running
4operational

Projects within 10 km of BL9

Projects of 1 MW and more (19)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Lascar Worksbattery storagebattery storage20operationalupdated Jul 2019Nov 2017granted May 2018Jul 2019Bury0.8
Chamber Housesolar farmsolar farm4under constructionupdated Oct 2023Jun 2020granted Aug 2020Oct 2023Rochdale4.9
The Rake, Lower Jowkin Lanebattery storagebattery storage57approved, not builtupdated May 2024Jul 2023granted Apr 2024May 2024Rochdale5.6
Shore Top Farm, Kearsley Roadbattery storagebattery storage11approved, not builtupdated Dec 2025Jun 2025granted Nov 2025Dec 2025Bury6.3
Stonecloughbattery storagebattery storage7approved, not built may be out of dateupdated May 2022Apr 2022granted Oct 2022May 2022Bolton6.8
Astra Centre, Royal Barn Roadbattery storagebattery storage40under constructionupdated Feb 2024Sep 2021granted Nov 2021Feb 2024Rochdale7.2
Gipsy Lanebattery storagebattery storage20under constructionupdated Jul 2021Nov 2019granted Mar 2020Jul 2021Rochdale7.2
Robert McBride Ltdrooftop solarrooftop solar1.3permission expiredupdated Aug 2018Mar 2015granted Apr 2015Aug 2018Rochdale7.5
Tesco Distribution Centre, Stakehill Industrial Estaterooftop solarrooftop solar1approved, not builtupdated Apr 2024Feb 2024granted Apr 2024Apr 2024Rochdale8.1
Rochdale Road, Edenfieldbattery storagebattery storage85refusedupdated Oct 2025Apr 2025refused Sep 2025Oct 2025Rossendale8.5
Rooley Moorwind farmwind farm39.6appeal withdrawnupdated Jan 2016Aug 2014refused Jul 2015Jan 2016Rochdale8.6
Scout Moor Windfarmwind farmwind farm65operationalupdated Feb 2018Jun 2003granted May 2005Feb 2018Rossendale8.6
Scout Moor Windfarm (extension)wind farmwind farm36.8refusedupdated Jul 2017Apr 2015refused Jul 2017Jul 2017Rossendale8.6
Union Court Storage Facilitybattery storagebattery storage4.8approved, not built may be out of dateupdated Dec 2021Jul 2021granted Oct 2021Dec 2021Bolton8.8
Bent Spur Solar Farmsolar farmsolar farm5operationalupdated Apr 2016Aug 2015granted Nov 2015Apr 2016Bolton8.8
Miall Power Energy Storage Facilitybattery storagebattery storage5refusedupdated Apr 2021Feb 2021refused Jun 2021Apr 2021Rochdale9.2
The Stables (Edgeworth)wind farmwind farm2.6refusedupdated Nov 2007Jul 2003refused Oct 2004Nov 2007Blackburn with Darwen9.3
Salford Roadrooftop solarrooftop solar1.6operationalupdated Jun 2016——Jun 2016Bolton9.3
Edbro, Lever Streetrooftop solarrooftop solar1.7approved, not built may be out of dateupdated Jun 2023Apr 2023granted Jun 2023Jun 2023Bolton9.7
Smaller schemes under 1 MW, mostly rooftop solar (25)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Food Warehouse Iceland, Pilsworth Road -Solar Panelsrooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Dec 2025granted Jan 2026Apr 2026Bury1.8
Heywood Distribution Park, Pilsworth Roadrooftop solarrooftop solar0.1approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026Rochdale2.5
Heywood Distribution Park, Pilsworth Roadrooftop solarrooftop solar0.1approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Rochdale2.5
Heywood Sports Villagerooftop solarrooftop solar0.1approved, not builtupdated Jun 2021Jun 2021granted Aug 2021Jun 2021Rochdale4.0
Park 17 Industrial Estaterooftop solarrooftop solar0.2approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024Bury4.5
David Lloyd Health Club, Heywood Old Roadrooftop solarrooftop solar0.6approved, not builtupdated Dec 2023Aug 2023granted Nov 2023Dec 2023Rochdale5.5
Polyflor Limited, Prestwich Delivery Officerooftop solarrooftop solar—approved, not builtupdated Jul 2025Apr 2025granted Jul 2025Jul 2025Bury6.4
Norden Community School Solar PV Systemsrooftop solarrooftop solar0.2approved, not builtupdated Jun 2021Jun 2021granted Aug 2021Jun 2021Rochdale6.6
Sainsburys Supermarkets, Heaton Park Roadrooftop solarrooftop solar0.3application submittedMay 2026——Manchester6.9
Hopwood Hall College, Rochdale Roadrooftop solarrooftop solar0.5application submittedupdated Sep 2024Aug 2024—Sep 2024Rochdale7.0
Gipsy Lane Battery Energy Storage Facilitybattery storagebattery storage—application withdrawnupdated Jan 2019Oct 2018—Jan 2019Rochdale7.2
Cardinal Langley RC High School, Rochdale Roadrooftop solarrooftop solar0.4approved, not builtupdated Nov 2025Jul 2025granted Sep 2025Nov 2025Rochdale7.5
Europa Way, Units F1 & F2rooftop solarrooftop solar0.9refusedupdated May 2022Feb 2022refused Mar 2023May 2022Bolton7.6
Spotland Stadium, Sandy Lanerooftop solarrooftop solar0.1approved, not builtupdated Jan 2025Nov 2024granted Dec 2024Jan 2025Rochdale7.7
The West Side Of Hanson Street, Middletonbattery storagebattery storage0.2application submitted may be out of dateupdated Feb 2023Feb 2023—Feb 2023Rochdale7.8
Moss Rose Millrooftop solarrooftop solar0.3approved, not builtupdated Dec 2024Oct 2024granted Dec 2024Dec 2024Bolton8.3
Crompton Health Centre, Crompton Wayrooftop solarrooftop solar0.2approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Bolton8.5
Vernacare, Folds Roadrooftop solarrooftop solar0.7approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Bolton8.8
Albion Mill, Cawdor Streetrooftop solarrooftop solar0.5approved, not builtupdated Jun 2025Apr 2025granted Jun 2025Jun 2025Bolton8.9
City Of Salford Highway Services, Swinton Hall Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated May 2023May 2023granted Jul 2023May 2023Salford9.4
Jj Food Service, 1A Lamplight Wayrooftop solarrooftop solar0.4approved, not builtupdated Nov 2023Aug 2023granted Nov 2023Nov 2023Salford9.6
Broughton Hub, Rigby Streetrooftop solarrooftop solar0.2approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024Salford9.6
Foxdenton Lane, Chaddertonrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Dec 2024granted Jan 2025Jan 2025Oldham9.7
Oldham Broadway Business Park Solar Panelsrooftop solarrooftop solar—approved, not builtupdated Mar 2021Feb 2021granted Apr 2021Mar 2021Oldham9.8
Inkech, Crawford Streetrooftop solarrooftop solar0.2approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025Rochdale9.9

Distance from the average position of the BL9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm201104
Rooftop solar27222118.4
Wind farm400120
Battery storage111612140

MW in pipeline: pending, approved and under-construction capacity.

How Bury decides solar, wind and battery applications

Bury has 5 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in Bury

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BL9, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.