Energy Projects Near You

Astra Centre, Royal Barn Road (40 MW battery storage)

Astra Centre, Royal Barn Road is a 40 MW battery storage project in Rochdale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 27 February 2024; the record was last updated on 29 February 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWbattery storage
under constructionstatus in REPD
29 February 2024record last updated
Rochdalecouncil area

Planning timeline

DateStage
2 September 2021Application submitted
1 November 2021Planning permission granted
27 February 2024Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
40 MW
Status (REPD)
under construction
Record last updated
29 February 2024
Operator or applicant
Arlington Energy Limited
Planning authority
Rochdale
Planning application reference
21/01098/FUL
Address (REPD)
R/o Astra Centre, Royal Barn Road, Rochdale
Council area (by location)
Rochdale
Time to decision
9 weeks
Name in REPD
Astra Centre, Royal Barn Road - Energy Storage
REPD reference
9584

Who decides

ApplicationsRochdaleUK
Decided applications (solar, wind, battery)2610,236
Refused4 (15%)19%
Solar refused0 of 1412%
Onshore wind refused3 of 645%
Battery storage refused1 of 616%
Median time from submission to decision10.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Gipsy Lanebattery storage20under construction0.1
Miall Power Energy Storage Facilitybattery storage5refused2.4
The Rake, Lower Jowkin Lanebattery storage57approved, not built3.5
Ellenroad Farm, Bentgate Streetbattery storage30approved, not built4.7
Rooley Moorwind farm39.6appeal withdrawn6.8
Whitegate Battery Storagebattery storage57under construction7.2
Chaddertonbattery storage20under construction7.3
Great Hill Wind Farmwind farm10.1refused7.5
Lascar Worksbattery storage20operational7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5966, -2.1789).