Charnock Richard (30 MW battery storage)

Charnock Richard is a 30 MW battery storage project in Chorley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 3 February 2026; the record was last updated on 5 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWbattery storage
operationalstatus in REPD
5 March 2026record last updated
Chorleycouncil area

Planning timeline

DateStage
22 February 2022Application submitted
27 May 2022Planning permission granted
3 February 2026Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
30 MW
Status (REPD)
operational
Record last updated
5 March 2026
Operator or applicant
Pulse Clean Energy
Planning authority
Chorley
Planning application reference
22/00204/FUL
Address (REPD)
Scrap Yard Town Lane Charnock Richard Chorley
Council area (by location)
Chorley
Time to decision
13 weeks
Name in REPD
Charnock Richard - Battery Storage
REPD reference
20393

Who decides

Chorley has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Vause Farmbattery storage20approved, not built<0.1
Thompson House Equestrian farmsolar farm5operational1.9
Green Energy Park, Eyes Lanesolar farm12application submitted6.0
Green Energy Park, Eyes Lanebattery storage5application submitted6.0
Wanes Blades Road Solar Farmsolar farm16refused7.1
Land off Tithe Barn lanesolar farm5refused8.9
Tithe Barn Lanesolar8refused8.9
Tontine Roadbattery storage70application submitted8.9
Kilshaw Streetbattery storage20permission expired9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6144, -2.6884).