Green Energy Park, Eyes Lane (12 MW)
Green Energy Park, Eyes Lane is a 12 MW solar farm project in Chorley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 14 January 2026, no decision recorded; the record was last updated on 9 April 2026.
12 MWsolar farm
application submittedstatus in REPD
9 April 2026record last updated
Chorleycouncil area
Planning timeline
| Date | Stage |
|---|---|
| 14 January 2026 | Application submitted |
Project details
- Technology
- solar farm
- Capacity
- 12 MW
- Status (REPD)
- application submitted
- Record last updated
- 9 April 2026
- Operator or applicant
- GA Pet Food Partners Group Limited
- Planning authority
- Chorley
- Planning application reference
- 25/01256/FULMAJ
- Site area
- 39.7 ha
- Address (REPD)
- Green Energy Park, Asland Walks Eyes Lane, Bretherton, Chorley
- Council area (by location)
- Chorley
- Name in REPD
- Green Energy Park, Eyes Lane - Solar panels
- REPD reference
- 18797
Who decides
Chorley has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Green Energy Park, Eyes Lane | battery storage | 5 | application submitted | <0.1 |
| Tithe Barn Lane | solar | 8 | refused | 2.9 |
| Land off Tithe Barn lane | solar farm | 5 | refused | 2.9 |
| Charnock Richard | battery storage | 30 | operational | 6.0 |
| Vause Farm | battery storage | 20 | approved, not built | 6.0 |
| Thompson House Equestrian farm | solar farm | 5 | operational | 7.3 |
| The Glowhouse | battery storage | 5 | under construction | 8.1 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6532, -2.6252).