The Glowhouse (5 MW battery storage)

The Glowhouse is a 5 MW battery storage project in South Ribble, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 January 2022; the record was last updated on 7 February 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWbattery storage
under constructionstatus in REPD
7 February 2021record last updated
South Ribblecouncil area

Planning timeline

DateStage
7 September 2020Application submitted
21 October 2020Planning permission granted
1 January 2022Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
5 MW
Status (REPD)
under construction
Record last updated
7 February 2021
Operator or applicant
AMP Clean Energy
Planning authority
South Ribble
Planning application reference
07/2020/00739/FUL
Address (REPD)
The Glowhouse Limited, Moss Side Industrial Estate, Leyland,
Council area (by location)
South Ribble
Time to decision
6 weeks
REPD reference
8031

Who decides

ApplicationsSouth RibbleUK
Decided applications (solar, wind, battery)1310,236
Refused0 (0%)19%
Solar refused0 of 912%
Battery storage refused0 of 416%
Median time from submission to decision6.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Howick Hall Farmbattery storage49.9application submitted5.6
Penworthambattery storage57approved, not built5.8
Penwortham Sub Stationbattery storage50permission expired5.9
Green Energy Park, Eyes Lanesolar farm12application submitted8.1
Green Energy Park, Eyes Lanebattery storage5application submitted8.1
Tithe Barn Lanesolar8refused8.4
Land off Tithe Barn lanesolar farm5refused8.4
Clifton Marsh Farm, Preston New Road Solar Farmsolar farm49.9application submitted9.1
Charnock Richardbattery storage30operational9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6987, -2.7221).