Energy Projects Near You

Penwortham Sub Station (50 MW battery storage)

Penwortham Sub Station is a 50 MW battery storage project in South Ribble, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 16 November 2020; the record was last updated on 21 August 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
permission expiredstatus in REPD
21 August 2020record last updated
South Ribblecouncil area

Planning timeline

DateStage
18 September 2017Application submitted
14 May 2021Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
permission expired
Record last updated
21 August 2020
Operator or applicant
Statera Energy
Planning authority
South Ribble
Planning application reference
07/2017/2821/FUL
Address (REPD)
Howick Hall Farm, Howick Cross Lane, Penwortham, Preston
Council area (by location)
South Ribble
Time to decision
191 weeks
REPD reference
7119

Who decides

ApplicationsSouth RibbleUK
Decided applications (solar, wind, battery)1310,236
Refused0 (0%)19%
Solar refused0 of 912%
Battery storage refused0 of 416%
Median time from submission to decision6.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Penworthambattery storage57approved, not built0.1
Howick Hall Farmbattery storage49.9application submitted0.5
Clifton Marsh Farm, Preston New Road Solar Farmsolar farm49.9application submitted4.1
Oakfield Farmsolar farm5operational4.4
The Glowhousebattery storage5under construction5.9
Cooper House Farmsolar farm5operational8.0
Newfold Solar Farmsolar farm5abandoned9.0
Lower House Farm, Lewth Lane Solar Farmsolar farm20approved, not built9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7474, -2.7581).