Energy Projects Near You

Oakfield Farm (5 MW solar farm)

Oakfield Farm is a 5 MW solar farm project in Fylde, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2016; the record was last updated on 31 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
31 October 2016record last updated
Fyldecouncil area

Planning timeline

DateStage
20 January 2015Application submitted
1 April 2015Planning permission granted
31 January 2016Construction started
31 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
31 October 2016
Operator or applicant
Renewable Source
Planning authority
Fylde
Planning application reference
14/0811
Site area
11.3 ha
Address (REPD)
Oakfield Farm, Preston
Council area (by location)
Fylde
Time to decision
10 weeks
REPD reference
6230

Who decides

ApplicationsFyldeUK
Decided applications (solar, wind, battery)1910,236
Refused3 (16%)19%
Solar refused3 of 1612%
Battery storage refused0 of 316%
Median time from submission to decision19.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Clifton Marsh Farm, Preston New Road Solar Farmsolar farm49.9application submitted1.6
Cooper House Farmsolar farm5operational4.4
Penwortham Sub Stationbattery storage50permission expired4.4
Penworthambattery storage57approved, not built4.5
Howick Hall Farmbattery storage49.9application submitted4.9
Newfold Solar Farmsolar farm5abandoned5.2
Lower House Farm, Lewth Lane Solar Farmsolar farm20approved, not built6.0
Land off Moss Side Lanesolar farm5operational7.9
Bilsborrow Solar Farmsolar farm5operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7719, -2.8103).