Bilsborrow Solar Farm (5 MW)

Bilsborrow Solar Farm is a 5 MW solar farm project in Wyre, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2017; the record was last updated on 4 December 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
4 December 2017record last updated
Wyrecouncil area

Planning timeline

DateStage
23 March 2015Application submitted
15 June 2015Planning permission granted
12 December 2016Construction started
30 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
4 December 2017
Operator or applicant
Greencoat Capital
Planning authority
Wyre
Planning application reference
15/00260/LMAJ
Site area
13.0 ha
Address (REPD)
Land Off, Moss Lane, Bilsborrow, Preston,
Council area (by location)
Wyre
Time to decision
12 weeks
REPD reference
5163

Earlier applications for this site

ApplicationMWSubmittedOutcome
Bilsborrow Solar Farm 14/00558/LMAJ154 July 2014refused 17 November 2014

Who decides

ApplicationsWyreUK
Decided applications (solar, wind, battery)1910,236
Refused4 (21%)19%
Solar refused1 of 1112%
Onshore wind refused3 of 445%
Battery storage refused0 of 416%
Median time from submission to decision19.4 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mount Pleasant Farm, Green Lanebattery storage45under construction2.4
Westfield Farmsolar farm5operational3.0
Lower House Farm, Lewth Lane Solar Farmsolar farm20approved, not built3.4
Turners Lane, Barnacre Solar Farmsolar farm23approved, not built5.9
Snapewood Solar Farmsolar farm10approved, not built8.8
Oakfield Farmsolar farm5operational8.9
Eagland Hillsolar farm15application submitted9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8457, -2.7596).