Energy Projects Near You

Mount Pleasant Farm, Green Lane (45 MW battery storage)

Mount Pleasant Farm, Green Lane is a 45 MW battery storage project in Wyre, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 October 2025; the record was last updated on 19 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

45 MWbattery storage
under constructionstatus in REPD
19 May 2026record last updated
Wyrecouncil area

Planning timeline

DateStage
22 December 2022Application submitted
3 October 2023Planning permission granted
1 October 2025Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
45 MW
Status (REPD)
under construction
Record last updated
19 May 2026
Operator or applicant
Barton Battery Storage
Planning authority
Wyre
Planning application reference
06/2022/0763
Address (REPD)
Adjacent Mount Pleasant Farm, Green Lane, Barton
Council area (by location)
Wyre
Time to decision
41 weeks
Name in REPD
Mount Pleasant Farm, Green Lane - Battery Storage
REPD reference
13011

Who decides

ApplicationsWyreUK
Decided applications (solar, wind, battery)1910,236
Refused4 (21%)19%
Solar refused1 of 1112%
Onshore wind refused3 of 445%
Battery storage refused0 of 416%
Median time from submission to decision19.4 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bilsborrow Solar Farmsolar farm5operational2.4
Westfield Farmsolar farm5operational3.5
Turners Lane, Barnacre Solar Farmsolar farm23approved, not built5.2
Lower House Farm, Lewth Lane Solar Farmsolar farm20approved, not built5.8
Snapewood Solar Farmsolar farm10approved, not built9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8528, -2.7242).