Westfield Farm (5 MW solar farm)

Westfield Farm is a 5 MW solar farm project in Wyre, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 January 2016; the record was last updated on 1 February 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
1 February 2016record last updated
Wyrecouncil area

Planning timeline

DateStage
12 November 2014Application submitted
6 May 2015Planning permission granted
1 November 2015Construction started
15 January 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
1 February 2016
Operator or applicant
Hive Energy/ Vogt Solar
Planning authority
Wyre
Planning application reference
14/00909/LMAJ
Address (REPD)
Westfield Farm, Catterall
Council area (by location)
Wyre
Time to decision
25 weeks
REPD reference
4887

Who decides

ApplicationsWyreUK
Decided applications (solar, wind, battery)1910,236
Refused4 (21%)19%
Solar refused1 of 1112%
Onshore wind refused3 of 445%
Battery storage refused0 of 416%
Median time from submission to decision19.4 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bilsborrow Solar Farmsolar farm5operational3.0
Turners Lane, Barnacre Solar Farmsolar farm23approved, not built3.1
Mount Pleasant Farm, Green Lanebattery storage45under construction3.5
Lower House Farm, Lewth Lane Solar Farmsolar farm20approved, not built5.7
Snapewood Solar Farmsolar farm10approved, not built5.9
Eagland Hillsolar farm15application submitted7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8726, -2.7654).