Newfold Solar Farm (5 MW)

Newfold Solar Farm is a 5 MW solar farm project in Fylde, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 24 October 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
abandonedstatus in REPD
24 October 2018record last updated
Fyldecouncil area

Planning timeline

DateStage
27 August 2015Application submitted
15 December 2015Planning permission granted
14 December 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
24 October 2018
Operator or applicant
New Energy for the World
Planning authority
Fylde
Planning application reference
15/0501
Address (REPD)
Newfold Farm, Brown Lane, Wrea Green, Preston
Council area (by location)
Fylde
Time to decision
16 weeks
REPD reference
5717

Who decides

ApplicationsFyldeUK
Decided applications (solar, wind, battery)1910,236
Refused3 (16%)19%
Solar refused3 of 1612%
Battery storage refused0 of 316%
Median time from submission to decision19.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cooper House Farmsolar farm5operational0.9
Land off Moss Side Lanesolar farm5operational2.7
Lowland Farm, Peel Roadbattery storage100application submitted4.7
Clifton Marsh Farm, Preston New Road Solar Farmsolar farm49.9application submitted4.9
Lawns Solar Farmsolar farm25approved, not built5.2
Oakfield Farmsolar farm5operational5.2
West Moss Lane, Higher Ballambattery storage30approved, not built5.6
Peel Road Phase 2 Solar Farmsolar farm13application submitted6.0
Peel Roadbattery storage20approved, not built6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7692, -2.8898).