Energy Projects Near You

Lawns Solar Farm (25 MW)

Lawns Solar Farm is a 25 MW solar farm project in Fylde, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 1 February 2023, not yet built; the record was last updated on 1 February 2023. REPD records the planning permission as expiring on 1 February 2026, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWsolar farm
approved, not builtmay be out of datestatus in REPD
1 February 2023record last updated
Fyldecouncil area

REPD records the planning permission as expiring on 1 February 2026, but the project holds a Contracts for Difference award (AR5), so construction may have started.

Planning timeline

DateStage
19 October 2021Application submitted
1 February 2023Planning permission granted
1 February 2026Permission expired

Project details

Technology
solar farm
Capacity
25 MW
Status (REPD)
approved, not built
Record last updated
1 February 2023
Operator or applicant
Lightsource Limited
Planning authority
Fylde
Planning application reference
21/0904
Site area
30.3 ha
Address (REPD)
E/O Peel Road Lawns Farm, Ballam Road, Westby With Plumptons, Lytham St Annes
Council area (by location)
Fylde
Time to decision
67 weeks
Contracts for Difference
AR5
REPD reference
9878

Who decides

ApplicationsFyldeUK
Decided applications (solar, wind, battery)1910,236
Refused3 (16%)19%
Solar refused3 of 1612%
Battery storage refused0 of 316%
Median time from submission to decision19.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lowland Farm, Peel Roadbattery storage100application submitted0.5
West Moss Lane, Higher Ballambattery storage30approved, not built1.0
Peel Roadbattery storage20approved, not built1.2
Peel Road Phase 2 Solar Farmsolar farm13application submitted1.2
Land off Moss Side Lanesolar farm5operational2.6
Cask Farmsolar farm5refused3.6
Newfold Solar Farmsolar farm5abandoned5.2
Smithy Lane, Staining Solar PV Panels & BESSsolar farm40application submitted5.5
Cooper House Farmsolar farm5operational6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7734, -2.9687).