Cooper House Farm (5 MW solar farm)

Cooper House Farm is a 5 MW solar farm project in Fylde, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2016; the record was last updated on 16 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
16 May 2016record last updated
Fyldecouncil area

Planning timeline

DateStage
13 May 2015Application submitted
6 November 2015Planning permission granted
15 January 2016Construction started
15 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
16 May 2016
Operator or applicant
Suncredit UK/ Vogt solar
Planning authority
Fylde
Planning application reference
15/0329
Site area
12.2 ha
Address (REPD)
Cooper House Farm, Kirkham Road, Freckleton, Preston, Lancashire
Council area (by location)
Fylde
Time to decision
25 weeks
REPD reference
5321

Who decides

ApplicationsFyldeUK
Decided applications (solar, wind, battery)1910,236
Refused3 (16%)19%
Solar refused3 of 1612%
Battery storage refused0 of 316%
Median time from submission to decision19.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Newfold Solar Farmsolar farm5abandoned0.9
Land off Moss Side Lanesolar farm5operational3.7
Clifton Marsh Farm, Preston New Road Solar Farmsolar farm49.9application submitted3.9
Oakfield Farmsolar farm5operational4.4
Lowland Farm, Peel Roadbattery storage100application submitted5.7
Lawns Solar Farmsolar farm25approved, not built6.1
West Moss Lane, Higher Ballambattery storage30approved, not built6.5
Peel Roadbattery storage20approved, not built6.9
Peel Road Phase 2 Solar Farmsolar farm13application submitted6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7664, -2.8762).