Solar, wind and battery projects near Preston (PR4)
29 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PR4 (Fylde): 4 are waiting for a planning decision, 12 approved but not yet running, 10 operational. The largest live scheme is Lowland Farm, Peel Road (100 MW battery storage, application submitted on 26 June 2025, no decision recorded), 8.7 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Burbo Bank (90 MW, operational), 37.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of PR4
Projects of 1 MW and more (23)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Clifton Marsh Waste Water Treatment Worksbattery storage | battery storage | 2 | operationalupdated Jun 2020 | Aug 2019 | granted Aug 2019 | Jun 2020 | Fylde | 0.5 |
| Clifton Marsh Wastewater Treatment Workssolar farm | solar farm | 1.3 | operationalupdated Sep 2019 | Aug 2017 | granted May 2018 | Sep 2019 | Fylde | 0.7 |
| Clifton Marsh Wastewater Treatment Workssolar farm | solar farm | 3.2 | operationalupdated Sep 2019 | Nov 2017 | granted Aug 2018 | Sep 2019 | Fylde | 0.7 |
| Clifton Marsh Wwtwsolar farm | solar farm | 4.5 | refusedupdated Jan 2017 | Jan 2016 | refused Jan 2017 | Jan 2017 | Fylde | 0.8 |
| Clifton Marsh Farm, Preston New Road Solar Farmsolar farm | solar farm | 49.9 | application submitted may be out of dateupdated Aug 2024 | Jul 2024 | — | Aug 2024 | Fylde | 1.0 |
| Oakfield Farmsolar farm | solar farm | 5 | operationalupdated Oct 2016 | Jan 2015 | granted Apr 2015 | Oct 2016 | Fylde | 2.3 |
| Oakfield Farm - extensionsolar farm | solar farm | 1.7 | operationalupdated Oct 2016 | Oct 2015 | granted Dec 2015 | Oct 2016 | Fylde | 2.4 |
| Cooper House Farmsolar farm | solar farm | 5 | operationalupdated May 2016 | May 2015 | granted Nov 2015 | May 2016 | Fylde | 3.1 |
| Newfold Solar Farmsolar farm | solar farm | 5 | abandonedupdated Oct 2018 | Aug 2015 | granted Dec 2015 | Oct 2018 | Fylde | 4.1 |
| Penwortham Sub Stationbattery storage | battery storage | 50 | permission expiredupdated Aug 2020 | Sep 2017 | granted May 2021 | Aug 2020 | South Ribble | 5.0 |
| Penworthambattery storage | battery storage | 57 | approved, not built may be out of dateupdated May 2022 | Apr 2022 | granted Apr 2022 | May 2022 | South Ribble | 5.1 |
| Howick Hall Farmbattery storage | battery storage | 49.9 | application submitted may be out of dateupdated Mar 2021 | Jan 2021 | — | Mar 2021 | South Ribble | 5.5 |
| Three Nooks Wood, Weeton Roadrooftop solar | rooftop solar | 1.3 | approved, not built may be out of dateupdated Mar 2023 | Feb 2023 | granted Mar 2023 | Mar 2023 | Fylde | 5.6 |
| Carver Hay, moss lanesolar farm | solar farm | 2.5 | operationalupdated Apr 2017 | Oct 2015 | granted Dec 2015 | Apr 2017 | South Ribble | 6.5 |
| Land off Moss Side Lanesolar farm | solar farm | 5 | operationalupdated Dec 2017 | Aug 2015 | granted Nov 2015 | Dec 2017 | Fylde | 6.8 |
| Lower House Farm, Lewth Lane Solar Farmsolar farm | solar farm | 20 | approved, not builtupdated Dec 2025 | Feb 2025 | granted Nov 2025 | Dec 2025 | Wyre | 8.0 |
| Lowland Farm, Peel Roadbattery storage | battery storage | 100 | application submittedupdated Aug 2025 | Jun 2025 | — | Aug 2025 | Fylde | 8.7 |
| Staining Wood Farmsolar farm | solar farm | 4.9 | operationalupdated Aug 2016 | May 2015 | granted Sep 2015 | Aug 2016 | Fylde | 8.8 |
| Lawns Solar Farmsolar farm | solar farm | 25 | approved, not built may be out of dateupdated Feb 2023 | Oct 2021 | granted Feb 2023 | Feb 2023 | Fylde | 9.2 |
| West Moss Lane, Higher Ballambattery storage | battery storage | 30 | approved, not builtupdated May 2025 | Jul 2024 | granted Apr 2025 | May 2025 | Fylde | 9.4 |
| The Glowhousebattery storage | battery storage | 5 | under constructionupdated Feb 2021 | Sep 2020 | granted Oct 2020 | Feb 2021 | South Ribble | 9.7 |
| Leyland Trucks, Croston Roadsolar farm | solar farm | 1.2 | application submitted | May 2026 | — | — | South Ribble | 9.8 |
| Leyland Trucks Limited, Croston Roadrooftop solar | rooftop solar | 4 | approved, not builtupdated May 2024 | Apr 2024 | granted May 2024 | May 2024 | South Ribble | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Vantage Toyota, Admiral Wayrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jul 2025 | Oct 2024 | granted Nov 2024 | Jul 2025 | Preston | 4.8 |
| WM Morrison Supermarket PV Solar Panelsrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2022 | Mar 2022 | granted May 2022 | Mar 2022 | Preston | 6.4 |
| Brookhouse Millrooftop solar | rooftop solar | 0.3 | operationalupdated Mar 2023 | Mar 2020 | granted Jul 2020 | Mar 2023 | Preston | 7.5 |
| Globe Mill, Midge Hall Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2024 | Mar 2024 | granted Apr 2024 | Apr 2024 | South Ribble | 8.3 |
| Preston College, St Vincents Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Jul 2025 | Aug 2025 | Preston | 9.2 |
| Preston North End Football Stadium, Sir Tom Finney Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2025 | Feb 2025 | granted Apr 2025 | Jul 2025 | Preston | 9.6 |
Distance from the average position of the PR4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 14 | 2 | 2 | 8 | 1 | 96.1 |
| Rooftop solar | 8 | 0 | 7 | 1 | 0 | 6.9 |
| Battery storage | 7 | 2 | 3 | 1 | 0 | 242 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Burbo Bank | 90 | operationalupdated Feb 2018 | 37.8 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Fylde decides solar, wind and battery applications
| Applications | Fylde | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 19 | 10,236 |
| Refused | 3 (16%) | 19% |
| Solar refused | 3 of 16 | 12% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 19.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PR4, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.