Renewable energy projects in Fylde

25 solar, wind or battery projects of 150 kW or more are located in Fylde (REPD, July 2026 extract): 6 pending, 6 approved but not running, 9 operational and 2 refused. The council refused 3 of 19 decided applications (16%; UK 19%), with a median 19 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25projects in the council area
6awaiting a decision
6approved, not running
16%of decisions refused

How Fylde decides

ApplicationsFyldeUK
Decided applications (solar, wind, battery)1910,236
Refused3 (16%)19%
Solar refused3 of 1612%
Battery storage refused0 of 316%
Median time from submission to decision19.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Projects in Fylde

Projects of 1 MW and more (21)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Lowland Farm, Peel Roadbattery storagebattery storage100application submittedupdated Aug 2025Jun 2025—Aug 2025
Clifton Marsh Farm, Preston New Road Solar Farmsolar farmsolar farm49.9application submitted may be out of dateupdated Aug 2024Jul 2024—Aug 2024
Smithy Lane, Staining Solar PV Panels & BESSsolar farmsolar farm40application submittedFeb 2026——
Smithy Lane, Staining Solar PV Panels & BESSbattery storagebattery storage40application submittedFeb 2026——
West Moss Lane, Higher Ballambattery storagebattery storage30approved, not builtupdated May 2025Jul 2024granted Apr 2025May 2025
Lawns Solar Farmsolar farmsolar farm25approved, not built may be out of dateupdated Feb 2023Oct 2021granted Feb 2023Feb 2023
Peel Roadbattery storagebattery storage20approved, not builtupdated Sep 2023Feb 2023granted Sep 2023Sep 2023
Peel Road Phase 2 Solar Farmsolar farmsolar farm13application submittedupdated Mar 2025Feb 2025—Mar 2025
Cooper House Farmsolar farmsolar farm5operationalupdated May 2016May 2015granted Nov 2015May 2016
Cask Farmsolar farmsolar farm5refusedupdated Nov 2015Jun 2015refused Oct 2015Nov 2015
Newfold Solar Farmsolar farmsolar farm5abandonedupdated Oct 2018Aug 2015granted Dec 2015Oct 2018
Land off Moss Side Lanesolar farmsolar farm5operationalupdated Dec 2017Aug 2015granted Nov 2015Dec 2017
Oakfield Farmsolar farmsolar farm5operationalupdated Oct 2016Jan 2015granted Apr 2015Oct 2016
Staining Wood Farmsolar farmsolar farm4.9operationalupdated Aug 2016May 2015granted Sep 2015Aug 2016
Land To The South Of Todderstaffesolar farmsolar farm4.5operationalupdated Jul 2017Jun 2015granted Nov 2015Jul 2017
Clifton Marsh Wwtwsolar farmsolar farm4.5refusedupdated Jan 2017Jan 2016refused Jan 2017Jan 2017
Clifton Marsh Wastewater Treatment Workssolar farmsolar farm3.2operationalupdated Sep 2019Nov 2017granted Aug 2018Sep 2019
Clifton Marsh Waste Water Treatment Worksbattery storagebattery storage2operationalupdated Jun 2020Aug 2019granted Aug 2019Jun 2020
Oakfield Farm - extensionsolar farmsolar farm1.7operationalupdated Oct 2016Oct 2015granted Dec 2015Oct 2016
Clifton Marsh Wastewater Treatment Workssolar farmsolar farm1.3operationalupdated Sep 2019Aug 2017granted May 2018Sep 2019
Three Nooks Wood, Weeton Roadrooftop solarrooftop solar1.3approved, not built may be out of dateupdated Mar 2023Feb 2023granted Mar 2023Mar 2023
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Weeton Barracks, Grantham Roadsolar farmsolar farm0.7under constructionupdated Feb 2025Apr 2024granted Sep 2024Feb 2025
Arnold Clark Blackpool Vauxhall, Whitehills Business Parkrooftop solarrooftop solar0.2application submittedJun 2026——
Merlewood Caravan Park, Cartford Lanesolar farmsolar farm0.1application withdrawnupdated Dec 2025Jun 2025—Dec 2025
National Car Parks, St Georges Roadrooftop solarrooftop solar—approved, not builtupdated Aug 2025Jun 2025granted Jul 2025Aug 2025

Postcode districts in Fylde

DistrictProjects within 10 kmPendingApprovedOperational
FY8265134
PR42941210

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Fylde by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.