Cask Farm (5 MW solar farm)

Cask Farm is a 5 MW solar farm project in Fylde, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 12 October 2015; the record was last updated on 5 November 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refusedstatus in REPD
5 November 2015record last updated
Fyldecouncil area

Planning timeline

DateStage
17 June 2015Application submitted
12 October 2015Refused by the planning authority

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
5 November 2015
Operator or applicant
Lightsource Renewable Energy
Planning authority
Fylde
Planning application reference
15/0406
Site area
15.4 ha
Address (REPD)
Cask Farm, Mythop Road, Weeton With Preese, Preston, Blackpool, Lancashire
Council area (by location)
Fylde
Time to decision
17 weeks
REPD reference
5484

Who decides

ApplicationsFyldeUK
Decided applications (solar, wind, battery)1910,236
Refused3 (16%)19%
Solar refused3 of 1612%
Battery storage refused0 of 316%
Median time from submission to decision19.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Smithy Lane, Staining Solar PV Panels & BESSsolar farm40application submitted2.3
Peel Roadbattery storage20approved, not built2.7
Peel Road Phase 2 Solar Farmsolar farm13application submitted2.7
Lawns Solar Farmsolar farm25approved, not built3.6
Lowland Farm, Peel Roadbattery storage100application submitted3.8
Land off Moss Side Lanesolar farm5operational4.1
Cocker Avenue Energy storage facilitybattery storage7.5approved, not built4.2
Aldon Roadbattery storage6permission expired4.2
West Moss Lane, Higher Ballambattery storage30approved, not built4.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8059, -2.9629).