Energy Projects Near You

Solar, wind and battery projects near Lytham St Annes (FY8)

26 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of FY8 (Fylde): 5 are waiting for a planning decision, 13 approved but not yet running, 4 operational. The largest live scheme is Lowland Farm, Peel Road (100 MW battery storage, application submitted on 26 June 2025, no decision recorded), 3.6 km away. Offshore, 4 wind farms are recorded within 40 km; the nearest is Burbo Bank (90 MW, operational), 31.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

26projects within 10 km
5awaiting a decision
13approved, not running
4operational

Projects within 10 km of FY8

Projects of 1 MW and more (14)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
West Moss Lane, Higher Ballambattery storagebattery storage30approved, not builtupdated May 2025Jul 2024granted Apr 2025May 2025Fylde2.4
Lawns Solar Farmsolar farmsolar farm25approved, not built may be out of dateupdated Feb 2023Oct 2021granted Feb 2023Feb 2023Fylde3.3
Lowland Farm, Peel Roadbattery storagebattery storage100application submittedupdated Aug 2025Jun 2025—Aug 2025Fylde3.6
Peel Roadbattery storagebattery storage20approved, not builtupdated Sep 2023Feb 2023granted Sep 2023Sep 2023Fylde4.0
Peel Road Phase 2 Solar Farmsolar farmsolar farm13application submittedupdated Mar 2025Feb 2025—Mar 2025Fylde4.0
Staining Wood Farmsolar farmsolar farm4.9operationalupdated Aug 2016May 2015granted Sep 2015Aug 2016Fylde4.3
Land off Moss Side Lanesolar farmsolar farm5operationalupdated Dec 2017Aug 2015granted Nov 2015Dec 2017Fylde5.5
Cask Farmsolar farmsolar farm5refusedupdated Nov 2015Jun 2015refused Oct 2015Nov 2015Fylde6.6
Newfold Solar Farmsolar farmsolar farm5abandonedupdated Oct 2018Aug 2015granted Dec 2015Oct 2018Fylde7.7
Smithy Lane, Staining Solar PV Panels & BESSsolar farmsolar farm40application submittedFeb 2026——Fylde8.0
Smithy Lane, Staining Solar PV Panels & BESSbattery storagebattery storage40application submittedFeb 2026——Fylde8.0
Land To The South Of Todderstaffesolar farmsolar farm4.5operationalupdated Jul 2017Jun 2015granted Nov 2015Jul 2017Fylde8.5
Cooper House Farmsolar farmsolar farm5operationalupdated May 2016May 2015granted Nov 2015May 2016Fylde8.5
Three Nooks Wood, Weeton Roadrooftop solarrooftop solar1.3approved, not built may be out of dateupdated Mar 2023Feb 2023granted Mar 2023Mar 2023Fylde8.6
Smaller schemes under 1 MW, mostly rooftop solar (12)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
National Car Parks, St Georges Roadrooftop solarrooftop solar—approved, not builtupdated Aug 2025Jun 2025granted Jul 2025Aug 2025Fylde1.9
Wallis Building Designs, Midgeland Roadsolar farmsolar farm0.2application withdrawnupdated Oct 2022Sep 2022—Oct 2022Blackpool2.9
Progress Waysolar farmsolar farm0.2application withdrawnupdated Oct 2022Sep 2022—Oct 2022Blackpool3.6
Arnold Clark Blackpool Vauxhall, Whitehills Business Parkrooftop solarrooftop solar0.2application submittedJun 2026——Fylde4.4
Tesco Stores, Clifton Retail Parkrooftop solarrooftop solar0.7approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Blackpool4.9
Blackpool Police Divisional Headquartersrooftop solarrooftop solar0.3approved, not builtupdated Jul 2023Apr 2023granted Jun 2023Jul 2023Blackpool5.0
St Georges Schoolrooftop solarrooftop solar0.5approved, not builtupdated Dec 2025Oct 2025granted Dec 2025Dec 2025Blackpool5.3
Marton Mere Holiday Village, Mythop Roadrooftop solarrooftop solar0.3approved, not builtupdated Apr 2023Feb 2023granted Apr 2023Apr 2023Blackpool5.8
Blackpool Victoria Hospitalrooftop solarrooftop solar0.1approved, not builtupdated Mar 2024Feb 2024granted Mar 2024Mar 2024Blackpool7.8
Weeton Barracks, Grantham Roadsolar farmsolar farm0.7under constructionupdated Feb 2025Apr 2024granted Sep 2024Feb 2025Fylde8.8
Crossens Pumping Stationbattery storagebattery storage—under constructionupdated Jun 2025Aug 2021granted Feb 2022Jun 2025Sefton9.1
Unity College, Warbreck Hill Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Blackpool9.7

Distance from the average position of the FY8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm12224178.7
Rooftop solar918003.7
Battery storage52300190

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Burbo Bank90operationalupdated Feb 201831.6
Barrow90operationalupdated Nov 201733.0
Burbo Bank Extension (Burbo Bank 2)258operationalupdated May 201834.9
West of Duddon Sands389operationalupdated Aug 202039.8

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Fylde decides solar, wind and battery applications

ApplicationsFyldeUK
Decided applications (solar, wind, battery)1910,236
Refused3 (16%)19%
Solar refused3 of 1612%
Battery storage refused0 of 316%
Median time from submission to decision19.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Fylde

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near FY8, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.