Barrow, one of the first offshore wind farms off Barrow-in-Furness, is modest by today's standards: 30 turbines of 3 MW each. The operator is Orsted (formerly Dong Energy). Its larger neighbours came later.
Consent in 44 weeks
The application was submitted on 10 May 2002, and on 12 March 2003 the minister granted consent under Section 36 (the register lists DECC as the authority). That is 44 weeks against a median of 95.8 for offshore wind, so twice as fast. Construction began on 1 May 2005, and power first flowed on 1 April 2006.
Walney and other neighbours
Searches for “Barrow-in-Furness wind farm” are often looking for Walney. Those are different projects: Walney 1 and Walney 2 at 184 MW each, and Walney 3 at 659 MW. Nearby you also have West of Duddon Sands (389 MW) and Ormonde (150 MW), while the application for Cirrus Shell Flat Array, at 284 MW, was withdrawn. The upshot: Barrow contributes 90 MW to the whole cluster, with the rest coming from the neighbours around LA14. Statuses are taken from the REPD extract for July 2026; anything decided since then does not yet show in the register.