Barrow offshore wind farm

Barrow is a 90 MW offshore wind farm with 30 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 April 2006; the record was last updated on 20 November 2017. Its REPD grid reference is 9 km from the nearest postcode on land (LA14 3YQ, Westmorland and Furness). It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

How it works ↓

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

90 MWoffshore wind farm
operationalstatus in REPD
20 November 2017record last updated
9 km from land (Westmorland and Furness)REPD location

Consent timeline

DateStage
10 May 2002Application submitted
12 March 2003Section 36 consent granted (Secretary of State)
1 May 2005Construction started
1 April 2006Operational

Project details

Technology
offshore wind farm
Capacity
90 MW
Turbines
30
Turbine capacity
3 MW
Status (REPD)
operational
Record last updated
20 November 2017
Operator or applicant
Orsted (formerly Dong Energy)
Consenting authority (REPD)
DECC (S36)
Application reference
not recorded
Nearest postcode on land
LA14 3YQ (Westmorland and Furness), 9.0 km from the REPD grid reference
Time to decision
44 weeks
REPD reference
2546

Who decides

It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Postcode districts within 40 km

Districtkm
Barrow-in-Furness (LA14)14.8
Barrow-in-Furness (LA13)15.5
Fleetwood (FY7)19.6
Dalton-in-Furness (LA15)19.8
Thornton-Cleveleys (FY5)22.3
Askam-in-Furness (LA16)22.6
Blackpool (FY2)23.4
Poulton-le-Fylde (FY6)24.9
Millom (LA18)25.0
Blackpool (FY1)25.6
Blackpool (FY3)26.2
Ulverston (LA12)27.4

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
West of Duddon Sands389operational10.7
Ormonde Offshore150operational14.2
Cirrus Shell Flat Array284application withdrawn14.9
Walney 1184operational15.2
Walney 2184operational22.6

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (53.9915, -3.2983).

Barrow, one of the first offshore wind farms off Barrow-in-Furness, is modest by today's standards: 30 turbines of 3 MW each. The operator is Orsted (formerly Dong Energy). Its larger neighbours came later.

The application was submitted on 10 May 2002, and on 12 March 2003 the minister granted consent under Section 36 (the register lists DECC as the authority). That is 44 weeks against a median of 95.8 for offshore wind, so twice as fast. Construction began on 1 May 2005, and power first flowed on 1 April 2006.

Walney and other neighbours

Searches for “Barrow-in-Furness wind farm” are often looking for Walney. Those are different projects: Walney 1 and Walney 2 at 184 MW each, and Walney 3 at 659 MW. Nearby you also have West of Duddon Sands (389 MW) and Ormonde (150 MW), while the application for Cirrus Shell Flat Array, at 284 MW, was withdrawn. The upshot: Barrow contributes 90 MW to the whole cluster, with the rest coming from the neighbours around LA14. Statuses are taken from the REPD extract for July 2026; anything decided since then does not yet show in the register.