Walney 3 offshore wind farm

Walney 3 is a 659 MW offshore wind farm with 87 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 13 September 2018; the record was last updated on 4 June 2020. Its REPD grid reference is 29 km from the nearest postcode on land (LA18 4NY, Cumberland). It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

659 MWoffshore wind farm
operationalstatus in REPD
4 June 2020record last updated
29 km from land (Cumberland)REPD location

Consent timeline

DateStage
30 July 2013Application submitted
7 November 2014Section 36 consent granted (Secretary of State)
1 April 2017Construction started
13 September 2018Operational

Project details

Technology
offshore wind farm
Capacity
659 MW
Turbines
87 (Ørsted; REPD: 110)
Turbine capacity
40 × 8 MW and 47 × 7 MW (Ørsted; REPD: 6 MW)
Turbine height
222 m
Status (REPD)
operational
Record last updated
4 June 2020
Operator or applicant
Orsted (formerly Dong Energy)
Consenting authority (REPD)
DECC (S36)
Application reference
not recorded
Nearest postcode on land
LA18 4NY (Cumberland), 29.3 km from the REPD grid reference
Time to decision
66 weeks
Contracts for Difference
Investment Contract
REPD reference
2533

Who decides

It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Postcode districts within 40 km

Districtkm
Millom (LA19)32.8
Millom (LA18)33.3
Barrow-in-Furness (LA14)33.3
Barrow-in-Furness (LA13)35.5
Askam-in-Furness (LA16)36.6
Ravenglass (CA18)37.1
Dalton-in-Furness (LA15)37.3
Seascale (CA20)40.0

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Walney 2184operational8.6
Walney 1184operational15.7
Ormonde Offshore150operational19.7
West of Duddon Sands389operational21.6

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (54.09, -3.74).