Solar, wind and battery projects near Barrow-in-Furness (LA13)
18 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LA13 (Westmorland and Furness): 5 are waiting for a planning decision, 6 approved but not yet running, 4 operational. The largest live scheme is Roosecote Power Station, Rampside Road (50 MW battery storage, application submitted on 27 August 2025, no decision recorded), 1.5 km away. Offshore, 6 wind farms are recorded within 40 km; the nearest is Barrow (90 MW, operational), 15.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of LA13
Projects of 1 MW and more (12)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Roosecote Power Station, Rampside Roadbattery storage | battery storage | 50 | application submittedupdated Oct 2025 | Aug 2025 | — | Oct 2025 | Westmorland and Furness | 1.5 |
| Roosecotebattery storage | battery storage | 49 | operationalupdated Nov 2018 | — | — | Nov 2018 | Westmorland and Furness | 1.5 |
| Dova Way, Barrow Islandsolar farm | solar farm | 2 | approved, not built may be out of dateupdated Mar 2023 | Nov 2022 | granted Mar 2023 | Mar 2023 | Westmorland and Furness | 2.6 |
| Cavendish Dock Roadfloating solar | floating solar | 40 | application submittedupdated Mar 2026 | Mar 2025 | — | Mar 2026 | Westmorland and Furness | 2.8 |
| Sowerby Lodge Farmsolar farm | solar farm | 5 | operationalupdated Sep 2018 | Oct 2014 | granted Feb 2015 | Sep 2018 | Westmorland and Furness | 3.6 |
| Sowerby Lodgesolar farm | solar farm | 4.2 | permission expiredupdated Dec 2019 | Mar 2015 | granted Feb 2016 | Dec 2019 | Westmorland and Furness | 3.7 |
| Sandscale Parksolar farm | solar farm | 2 | approved, not built may be out of dateupdated May 2022 | Nov 2022 | granted Mar 2023 | May 2022 | Westmorland and Furness | 3.8 |
| Bleabeck Solar Farmsolar farm | solar farm | 10 | application submittedupdated Mar 2025 | Feb 2025 | — | Mar 2025 | Westmorland and Furness | 6.0 |
| Solar Farm at Bleabeck Solar Farmsolar farm | solar farm | 10 | application submittedupdated Mar 2026 | Feb 2025 | — | Mar 2026 | Westmorland and Furness | 6.3 |
| Roanhead Farmsolar farm | solar farm | 6.5 | operationalupdated Dec 2015 | Jul 2014 | granted Sep 2014 | Dec 2015 | Westmorland and Furness | 6.3 |
| Hill Solar Farmsolar farm | solar farm | 5 | application withdrawnupdated Feb 2016 | Aug 2015 | — | Feb 2016 | Westmorland and Furness | 6.7 |
| Askamwind farm | wind farm | 4.6 | operationalupdated Dec 2019 | Mar 1995 | granted Oct 1997 | Dec 2019 | Westmorland and Furness | 7.4 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Barrow Leisure Centre, Greengate Streetrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Sep 2025 | May 2025 | granted Aug 2025 | Sep 2025 | Westmorland and Furness | 0.9 |
| Wm Morrison Supermarkets, The Strand PV equipmentrooftop solar | rooftop solar | 0.6 | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 | Westmorland and Furness | 2.0 |
| North Road - Roof Mounted Solar Arraysrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated May 2022 | Dec 2021 | granted Jan 2022 | May 2022 | Westmorland and Furness | 2.9 |
| JJC Waste Management, Sandscale Parkrooftop solar | rooftop solar | 0.7 | approved, not built may be out of dateupdated Aug 2023 | Jun 2023 | granted Jul 2023 | Aug 2023 | Westmorland and Furness | 4.4 |
| Greenhaume Farm, Askam Roadwind turbine | wind turbine | — | application submittedupdated Sep 2024 | Aug 2024 | — | Sep 2024 | Westmorland and Furness | 5.3 |
| Greenhaume Farm, Askam Roadwind turbine | wind turbine | — | refusedupdated Jan 2026 | Aug 2024 | refused Jan 2026 | Jan 2026 | Westmorland and Furness | 5.4 |
Distance from the average position of the LA13 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 8 | 2 | 2 | 2 | 0 | 24 |
| Rooftop solar | 4 | 0 | 4 | 0 | 0 | 1.7 |
| Floating solar | 1 | 1 | 0 | 0 | 0 | 40 |
| Wind farm | 1 | 0 | 0 | 1 | 0 | 0 |
| Wind turbine | 2 | 1 | 0 | 0 | 1 | 0 |
| Battery storage | 2 | 1 | 0 | 1 | 0 | 50 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Barrow | 90 | operationalupdated Nov 2017 | 15.5 |
| Ormonde Offshore | 150 | operationalupdated Aug 2017 | 16.0 |
| Walney 1 | 184 | operationalupdated Sep 2020 | 22.5 |
| West of Duddon Sands | 389 | operationalupdated Aug 2020 | 22.7 |
| Walney 2 | 184 | operationalupdated Sep 2020 | 27.1 |
| Walney 3 | 659 | operationalupdated Jun 2020 | 35.5 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Westmorland and Furness decides solar, wind and battery applications
| Applications | Westmorland and Furness | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 68 | 10,236 |
| Refused | 30 (44%) | 19% |
| Solar refused | 14 of 42 | 12% |
| Onshore wind refused | 14 of 19 | 45% |
| Battery storage refused | 2 of 7 | 16% |
| Median time from submission to decision | 34.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 9 / 9 | — |
All projects in Westmorland and Furness
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near LA13, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.