Energy Projects Near You

Solar, wind and battery projects near Ulverston (LA12)

16 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LA12 (Westmorland and Furness): 3 are waiting for a planning decision, 1 approved but not yet running, 5 operational. The largest live scheme is Solar Farm at Bleabeck Solar Farm (10 MW solar farm, application submitted on 20 February 2025, no decision recorded), 8.1 km away. Offshore, 5 wind farms are recorded within 40 km; the nearest is Ormonde Offshore (150 MW, operational), 26.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16projects within 10 km
3awaiting a decision
1approved, not running
5operational

Projects within 10 km of LA12

Projects of 1 MW and more (13)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Harlock Hill Wind Farmwind farmwind farm2.5operationalupdated Aug 2016Feb 1995granted May 1996Aug 2016Westmorland and Furness4.1
Furness Wind Farm/High Winds (Harlock Repowering)wind farmwind farm11.5operationalupdated Jun 2020Sep 2011granted Jul 2014Jun 2020Westmorland and Furness4.2
Gunson Height Wind Farmwind farmwind farm7.8refusedupdated Oct 2011Jan 1996refused Oct 1997Oct 2011Westmorland and Furness4.8
Lowick Beaconwind farmwind farm4.2refusedupdated Sep 2011Aug 2000refused Mar 2001Sep 2011Westmorland and Furness4.9
Lowick Beacon Windfarmwind farmwind farm1.2refusedupdated Oct 2011Jun 1995refused Oct 1997Oct 2011Westmorland and Furness5.0
Kirkby Moor Repoweringwind farmwind farm18refusedupdated Dec 2015Feb 2015refused Nov 2015Dec 2015Westmorland and Furness6.0
Askamwind farmwind farm4.6operationalupdated Dec 2019Mar 1995granted Oct 1997Dec 2019Westmorland and Furness6.7
Hill Solar Farmsolar farmsolar farm5application withdrawnupdated Feb 2016Aug 2015—Feb 2016Westmorland and Furness6.8
Kirkby Moorwind farmwind farm4.8operationalupdated Aug 2019Dec 2014granted Jun 2017Aug 2019Westmorland and Furness7.0
Land at Lane Headsolar farmsolar farm5refusedupdated Nov 2015Jul 2015refused Oct 2015Nov 2015Westmorland and Furness7.6
Solar Farm at Bleabeck Solar Farmsolar farmsolar farm10application submittedupdated Mar 2026Feb 2025—Mar 2026Westmorland and Furness8.1
Roanhead Farmsolar farmsolar farm6.5operationalupdated Dec 2015Jul 2014granted Sep 2014Dec 2015Westmorland and Furness8.8
Bleabeck Solar Farmsolar farmsolar farm10application submittedupdated Mar 2025Feb 2025—Mar 2025Westmorland and Furness9.4
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Greenhaume Farm, Askam Roadwind turbinewind turbine—application submittedupdated Sep 2024Aug 2024—Sep 2024Westmorland and Furness8.1
Greenhaume Farm, Askam Roadwind turbinewind turbine—refusedupdated Jan 2026Aug 2024refused Jan 2026Jan 2026Westmorland and Furness8.2
Lakeland Leisure Park, Moor Lane Solar Photovoltaics Equipmentrooftop solarrooftop solar0.3approved, not builtupdated Apr 2023Feb 2023granted Apr 2023Apr 2023Westmorland and Furness9.2

Distance from the average position of the LA12 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm5201120
Rooftop solar101000.3
Wind farm800440
Wind turbine210010

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Ormonde Offshore150operationalupdated Aug 201726.4
Barrow90operationalupdated Nov 201727.4
Walney 1184operationalupdated Sep 202033.5
West of Duddon Sands389operationalupdated Aug 202034.6
Walney 2184operationalupdated Sep 202036.8

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Westmorland and Furness decides solar, wind and battery applications

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

All projects in Westmorland and Furness

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.