Energy Projects Near You

Solar, wind and battery projects near Grange-Over-Sands (LA11)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LA11 (Westmorland and Furness): 1 approved but not yet running. The largest live scheme is Lakeland Leisure Park, Moor Lane Solar Photovoltaics Equipment (0.3 MW rooftop solar, approved on 14 April 2023, not yet built), 5.4 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Barrow (90 MW, operational), 33.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
0awaiting a decision
1approved, not running
0operational

Projects within 10 km of LA11

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Land at Lane Headsolar farmsolar farm5refusedupdated Nov 2015Jul 2015refused Oct 2015Nov 2015Westmorland and Furness3.7
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Lakeland Leisure Park, Moor Lane Solar Photovoltaics Equipmentrooftop solarrooftop solar0.3approved, not builtupdated Apr 2023Feb 2023granted Apr 2023Apr 2023Westmorland and Furness5.4

Distance from the average position of the LA11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm100010
Rooftop solar101000.3

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Barrow90operationalupdated Nov 201733.6
Ormonde Offshore150operationalupdated Aug 201735.6

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Westmorland and Furness decides solar, wind and battery applications

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

All projects in Westmorland and Furness

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.