Furness Wind Farm/High Winds (Harlock Repowering) (11.5 MW)

Furness Wind Farm/High Winds (Harlock Repowering) is an 11.5 MW wind farm project in Westmorland and Furness, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 17 November 2016; the record was last updated on 4 June 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.5 MWwind farm
operationalstatus in REPD
4 June 2020record last updated
Westmorland and Furnesscouncil area

Planning timeline

DateStage
6 September 2011Application submitted
21 May 2013Refused by the planning authority
24 July 2014Planning permission granted
24 July 2014Appeal allowed
20 December 2015Construction started
17 November 2016Operational

Project details

Technology
wind farm
Capacity
11.5 MW
Status (REPD)
operational
Record last updated
4 June 2020
Operator or applicant
Baywind Co-op & Energy4All & Belltown Power
Planning authority
Westmorland and Furness
Planning application reference
B06/2011/0662
Turbines
5
Address (REPD)
Standish Cote & Mean Moor, Pennington, Marton & Harlock Hill, Ulverston, Cumbria
Council area (by location)
Westmorland and Furness
Time to decision
150 weeks
REPD reference
4177

Who decides

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Gunson Height Wind Farmwind farm7.8refused2.4
Kirkby Moor Repoweringwind farm18refused3.4
Hill Solar Farmsolar farm5application withdrawn4.0
Solar Farm at Bleabeck Solar Farmsolar farm10application submitted5.1
Roanhead Farmsolar farm6.5operational5.6
Bleabeck Solar Farmsolar farm10application submitted6.2
Langthwaite Farmwind farm12application submitted9.7
Sowerby Lodge Farmsolar farm5operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.2091, -3.1476).