Furness Wind Farm/High Winds (Harlock Repowering) (11.5 MW)
Furness Wind Farm/High Winds (Harlock Repowering) is an 11.5 MW wind farm project in Westmorland and Furness, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 17 November 2016; the record was last updated on 4 June 2020.
11.5 MWwind farm
operationalstatus in REPD
4 June 2020record last updated
Westmorland and Furnesscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 6 September 2011 | Application submitted |
| 21 May 2013 | Refused by the planning authority |
| 24 July 2014 | Planning permission granted |
| 24 July 2014 | Appeal allowed |
| 20 December 2015 | Construction started |
| 17 November 2016 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 11.5 MW
- Status (REPD)
- operational
- Record last updated
- 4 June 2020
- Operator or applicant
- Baywind Co-op & Energy4All & Belltown Power
- Planning authority
- Westmorland and Furness
- Planning application reference
- B06/2011/0662
- Turbines
- 5
- Address (REPD)
- Standish Cote & Mean Moor, Pennington, Marton & Harlock Hill, Ulverston, Cumbria
- Council area (by location)
- Westmorland and Furness
- Time to decision
- 150 weeks
- REPD reference
- 4177
Who decides
| Applications | Westmorland and Furness | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 68 | 10,236 |
| Refused | 30 (44%) | 19% |
| Solar refused | 14 of 42 | 12% |
| Onshore wind refused | 14 of 19 | 45% |
| Battery storage refused | 2 of 7 | 16% |
| Median time from submission to decision | 34.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 9 / 9 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Gunson Height Wind Farm | wind farm | 7.8 | refused | 2.4 |
| Kirkby Moor Repowering | wind farm | 18 | refused | 3.4 |
| Hill Solar Farm | solar farm | 5 | application withdrawn | 4.0 |
| Solar Farm at Bleabeck Solar Farm | solar farm | 10 | application submitted | 5.1 |
| Roanhead Farm | solar farm | 6.5 | operational | 5.6 |
| Bleabeck Solar Farm | solar farm | 10 | application submitted | 6.2 |
| Langthwaite Farm | wind farm | 12 | application submitted | 9.7 |
| Sowerby Lodge Farm | solar farm | 5 | operational | 9.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.2091, -3.1476).