Gunson Height Wind Farm (7.8 MW)

Gunson Height Wind Farm is a 7.8 MW wind farm project in Westmorland and Furness, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 6 October 1997; the record was last updated on 30 October 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.8 MWwind farm
refusedstatus in REPD
30 October 2011record last updated
Westmorland and Furnesscouncil area

Planning timeline

DateStage
5 January 1996Application submitted
6 October 1997Refused by the planning authority

Project details

Technology
wind farm
Capacity
7.8 MW
Status (REPD)
refused
Record last updated
30 October 2011
Operator or applicant
RWE npower
Planning authority
Westmorland and Furness
Planning application reference
not recorded
Address (REPD)
Gunson Height Kirkby Moor Kirkby Ireleth Cumbria
Council area (by location)
Westmorland and Furness
Time to decision
91 weeks
REPD reference
2620

Who decides

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kirkby Moor Repoweringwind farm18refused1.3
Furness Wind Farm/High Winds (Harlock Repowering)wind farm11.5operational2.4
Hill Solar Farmsolar farm5application withdrawn6.3
Solar Farm at Bleabeck Solar Farmsolar farm10application submitted7.2
Roanhead Farmsolar farm6.5operational7.6
Bleabeck Solar Farmsolar farm10application submitted8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.2301, -3.1413).