Energy Projects Near You

Solar, wind and battery projects near Broughton-in-Furness (LA20)

5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LA20 (Westmorland and Furness): 1 operational. The largest scheme is Kirkby Moor Repowering (18 MW wind farm, refused on 26 November 2015), 7.0 km away. Offshore, 5 wind farms are recorded within 40 km; the nearest is Ormonde Offshore (150 MW, operational), 27.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects within 10 km
0awaiting a decision
0approved, not running
1operational

Projects within 10 km of LA20

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Kirkby Moorwind farmwind farm4.8operationalupdated Aug 2019Dec 2014granted Jun 2017Aug 2019Westmorland and Furness6.1
Kirkby Moor Repoweringwind farmwind farm18refusedupdated Dec 2015Feb 2015refused Nov 2015Dec 2015Westmorland and Furness7.0
Gunson Height Wind Farmwind farmwind farm7.8refusedupdated Oct 2011Jan 1996refused Oct 1997Oct 2011Westmorland and Furness8.2
Lowick Beacon Windfarmwind farmwind farm1.2refusedupdated Oct 2011Jun 1995refused Oct 1997Oct 2011Westmorland and Furness8.8
Lowick Beaconwind farmwind farm4.2refusedupdated Sep 2011Aug 2000refused Mar 2001Sep 2011Westmorland and Furness8.9

Distance from the average position of the LA20 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm500140

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Ormonde Offshore150operationalupdated Aug 201727.3
Barrow90operationalupdated Nov 201734.1
Walney 1184operationalupdated Sep 202034.7
Walney 2184operationalupdated Sep 202035.3
West of Duddon Sands389operationalupdated Aug 202038.1

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Westmorland and Furness decides solar, wind and battery applications

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

All projects in Westmorland and Furness

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.