Energy Projects Near You

Solar, wind and battery projects near Coniston (LA21)

1 solar, wind or battery project of 150 kW or more is recorded within 10 km of the centre of LA21 (Westmorland and Furness): 1 approved but not yet running. The largest live scheme is Low Wood Hotel (0.2 MW rooftop solar, approved on 9 March 2023, not yet built; REPD status may be out of date), 9.9 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Ormonde Offshore (150 MW, operational), 38.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1projects within 10 km
0awaiting a decision
1approved, not running
0operational

Projects within 10 km of LA21

Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Low Wood Hotelrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Mar 2023Dec 2022granted Mar 2023Mar 2023Westmorland and Furness9.9

Distance from the average position of the LA21 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar101000.2

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Ormonde Offshore150operationalupdated Aug 201738.5

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Westmorland and Furness decides solar, wind and battery applications

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

All projects in Westmorland and Furness

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near LA21, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.